Davis-Bacon rates (construction)
Minimum pay for laborers and mechanics on federal and federally funded construction over $2,000 in Dekalb County, Georgia.
Davis-Bacon Residential
Wage determination GA20260035, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Operating Engineer: Bulldozer | $28.32 | $13.45 | $41.77 |
| Operating Engineers: (Compactor And Loader) | $28.32 | $13.45 | $41.77 |
| Sheet Metal Worker: Including HVAC Duct Installation (Buildings Up To 100,000 Square Feet) | $25.49 | $11.73 | $37.22 |
| Sheet Metal Worker: Including HVAC Duct Installation (Buildings Over 100,000 Square Feet) | $32.60 | $15.52 | $48.12 |
| Truck Driver | $12.13 | $0.00 | $12.13 |
| Tile Setter | $11.07 | $0.00 | $11.07 |
| Roofer | $11.50 | $0.00 | $11.50 |
| Plumber, Excludes HVAC Pipe Installation | $12.67 | $0.00 | $12.67 |
| Painter: Brush, Roller And Spray, Excludes Drywall Finishing/Taping | $10.35 | $0.00 | $10.35 |
| Operator: Backhoe/Excavator | $13.69 | $0.00 | $13.69 |
| Laborer: Mason Tender | $8.00 | $0.00 | $8.00 |
| Laborer: Common Or General | $10.73 | $0.00 | $10.73 |
| HVAC Mechanic (HVAC Pipe Installation) | $11.14 | $0.00 | $11.14 |
| Form Worker | $8.50 | $0.16 | $8.66 |
| Electrician, Includes Installation Of Alarms | $10.63 | $0.00 | $10.63 |
| Drywall Hanger | $11.42 | $0.00 | $11.42 |
| Drywall Finisher/Taper | $13.45 | $0.00 | $13.45 |
| Cement Mason/Concrete Finisher | $10.01 | $0.34 | $10.35 |
| Carpenter, Excludes Drywall Hanging, And Form Work | $10.00 | $0.00 | $10.00 |
| Bricklayer | $13.83 | $0.00 | $13.83 |
Davis-Bacon Highway
Wage determination GA20260003, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Truck Driver: Lowboy Truck | $25.43 | $4.00 | $29.43 |
| Truck Driver: Dump Truck | $22.21 | $3.58 | $25.79 |
| Traffic Control: Flagger | $14.80 | $2.76 | $17.56 |
| Operator: Screed | $21.00 | $4.22 | $25.22 |
| Operator: Roller | $18.89 | $3.99 | $22.88 |
| Operator: Paver (Asphalt, Aggregate, And Concrete) | $23.62 | $4.10 | $27.72 |
| Operator: Milling Machine | $29.67 | $6.29 | $35.96 |
| Operator: Loader | $22.37 | $1.40 | $23.77 |
| Operator: Grader/Blade | $26.18 | $4.28 | $30.46 |
| Operator: Crane | $39.31 | $0.00 | $39.31 |
| Operator: Bulldozer | $24.68 | $2.59 | $27.27 |
| Operator: Backhoe/Excavator/Trackhoe | $23.53 | $3.63 | $27.16 |
| Laborer: Pipelayer | $22.42 | $0.00 | $22.42 |
| Laborer: Common Or General | $18.70 | $0.00 | $18.70 |
| Laborer: Asphalt, Includes Raker, Shoveler, Spreader And Distributor | $17.23 | $2.23 | $19.46 |
| Cement Mason/Concrete Finisher | $30.37 | $0.00 | $30.37 |
| Carpenter | $32.68 | $0.00 | $32.68 |
Davis-Bacon Heavy
Wage determination GA20260291, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Pipefitter | $24.72 | $13.82 | $38.54 |
| Operator: Roller | $11.89 | $0.00 | $11.89 |
| Operator: Loader | $17.86 | $0.65 | $18.51 |
| Operator: Crane | $25.45 | $0.00 | $25.45 |
| Operator: Bulldozer | $16.29 | $0.00 | $16.29 |
| Operator: Backhoe/Excavator/Trackhoe | $24.17 | $4.70 | $28.87 |
| Laborer: Pipelayer | $17.11 | $3.23 | $20.34 |
| Laborer: Common Or General | $13.98 | $1.38 | $15.36 |
| Electrician | $28.39 | $9.15 | $37.54 |
| Cement Mason/Concrete Finisher | $19.02 | $3.29 | $22.31 |
| Carpenter, Excludes Form Work | $21.64 | $3.90 | $25.54 |
| Carpenter (Form Work Only) | $19.99 | $0.00 | $19.99 |
Davis-Bacon Building
Wage determination GA20260305, revision 2, updated 1. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Asbestos Worker/Heat & Frost Insulator | $33.90 | $18.80 | $52.70 |
| Millwright | $31.58 | $17.05 | $48.63 |
| Electrician (Excludes Low Voltage Wiring) | $38.65 | $12.75 | $51.40 |
| Electrician (Low Voltage Wiring) | $38.65 | $12.75 | $51.40 |
| Operator: Backhoe/Excavator/Trackhoe | $28.32 | $13.45 | $41.77 |
| Operator: Crane | $38.53 | $16.08 | $54.61 |
| Operator: Forklift | $32.93 | $16.08 | $49.01 |
| Ironworker: Ornamental | $32.00 | $15.05 | $47.05 |
| Ironworker, Structural | $32.00 | $15.05 | $47.05 |
| Ironworker: Ornamental | $32.00 | $15.05 | $47.05 |
| Ironworker, Structural | $32.00 | $15.05 | $47.05 |
| Plumber | $41.18 | $17.01 | $58.19 |
| Pipefitter (HVAC Unit Installation Only) | $41.18 | $17.01 | $58.19 |
| Pipefitter (HVAC Pipe Installation Only) | $41.18 | $17.01 | $58.19 |
| Pipefitter (Excluding HVAC Pipe And Unit Installation) | $41.18 | $17.01 | $58.19 |
| Sheet Metal Worker (Including HVAC Duct Installation) | $38.29 | $17.40 | $55.69 |
| Painter: Spray | $16.29 | $0.00 | $16.29 |
| Painter (Brush And Roller) | $16.14 | $0.00 | $16.14 |
| Operator: Roller | $16.82 | $1.19 | $18.01 |
| Operator: Loader | $21.32 | $0.00 | $21.32 |
| Operator: Grader/Blade | $16.80 | $0.00 | $16.80 |
| Operator: Bulldozer | $15.23 | $0.00 | $15.23 |
| Operator: Bobcat/Skid Steer/Skid Loader | $20.24 | $0.00 | $20.24 |
| Laborer: Pipelayer | $12.55 | $1.90 | $14.45 |
| Laborer: Common Or General | $14.60 | $0.00 | $14.60 |
| Laborer: Asphalt, Includes Raker, Shoveler, Spreader And Distributor | $15.69 | $0.00 | $15.69 |
| Installer - Guardrail | $20.00 | $0.00 | $20.00 |
| Glazier | $21.77 | $6.36 | $28.13 |
| Cement Mason/Concrete Finisher | $13.35 | $0.00 | $13.35 |
| Carpenter, Excludes Form Work | $19.00 | $0.38 | $19.38 |
| Carpenter (Form Work Only) | $18.02 | $0.00 | $18.02 |
| Ironworker: Reinforcing | $31.31 | $17.68 | $48.99 |
Davis-Bacon Heavy
Wage determination GA20260058, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Operator: Loader | $21.77 | $0.00 | $21.77 |
| Operator: Grader/Blade | $25.82 | $1.81 | $27.63 |
| Operator: Backhoe/Excavator/Trackhoe | $24.89 | $0.00 | $24.89 |
| Laborer: Pipelayer | $16.08 | $0.00 | $16.08 |
| Laborer: Common Or General | $15.19 | $0.00 | $15.19 |
| Electrician | $28.40 | $0.52 | $28.92 |
| Cement Mason/Concrete Finisher | $19.30 | $2.43 | $21.73 |
| Carpenter (Form Work Only) | $20.51 | $0.01 | $20.52 |
Davis-Bacon Heavy
Wage determination GA20260059, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Operator: Loader | $21.77 | $0.00 | $21.77 |
| Operator: Grader/Blade | $25.82 | $1.81 | $27.63 |
| Operator: Backhoe/Excavator/Trackhoe | $24.89 | $0.00 | $24.89 |
| Laborer: Pipelayer | $16.08 | $0.00 | $16.08 |
| Laborer: Common Or General | $15.19 | $0.00 | $15.19 |
| Electrician | $28.40 | $0.52 | $28.92 |
| Cement Mason/Concrete Finisher | $19.30 | $2.43 | $21.73 |
| Carpenter (Form Work Only) | $20.51 | $0.01 | $20.52 |
Always price from the wage determination attached to the solicitation (and any amendment): it is the one that applies to that contract. Rates shown are copied from the public SAM.gov documents; check the official document before you bid.