Davis-Bacon rates (construction)
Minimum pay for laborers and mechanics on federal and federally funded construction over $2,000 in Dekalb Counties County, Illinois.
Davis-Bacon Building
Wage determination IL20260001, revision 6, updated 3. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Hazardous Material Handler: Includes Preparation, Wetting, Stripping Removal Scrapping, Vacuuming, Bagging And Disposal Of All Insulation Materials, Whether They Contain Asbestos Or Not, From Mechanical Systems (Bureau, De Kalb, La Salle, Lee, Livingston And Putnam Counties) | $41.27 | $32.76 | $74.03 |
| Fire Stop Technician (Bureau, De Kalb, La Salle, Lee, Livingston And Putnam Counties) | $44.02 | $32.76 | $76.78 |
| Asbestos Worker/Insulator: Includes The Application Of All Insulating Materials, Protective Coverings, Coatings, And Finishes To All Types Of Mechanical Systems (Bureau, De Kalb, La Salle, Lee, Livingston And Putnam Counties) | $55.02 | $35.75 | $90.77 |
| Hazardous Material Handler: Includes Preparation, Wetting, Stripping Removal Scrapping, Vacuuming, Bagging And Disposal Of All Insulation Materials, Whether They Contain Asbestos Or Not, From Mechanical Systems (Marshall, Mclean, Stark, And Woodford Counties) | $34.43 | $31.21 | $65.64 |
| Fire Stop Technician (Marshall, Mclean, Stark, And Woodford Counties) | $36.73 | $31.21 | $67.94 |
| Asbestos Worker/Insulator: Includes The Application Of All Insulating Materials, Protective Coverings, Coatings, And Finishes To All Types Of Mechanical Systems (Marshall, Mclean, Stark, And Woodford Counties) | $45.91 | $33.45 | $79.36 |
| Asbestos Workers/Insulator: Includes The Application Of All Insulating Materials, Protective Coverings, Coatings, And Finishes To All Types Of Mechanical Systems (Boone, Ogle, Stephenson, And Winnebago Counties) | $45.88 | $38.15 | $84.03 |
| Asbestos Workers/Insulator: Includes The Application Of All Insulating Materials, Protective Coverings, Coatings, And Finishes To All Types Of Mechanical Systems (Carroll, Hancock, Henderson, Henry, Jo Daviess, Knox, Mcdonough, Mercer, Rock Island, Warren, And Whiteside Counties) | $36.06 | $24.35 | $60.41 |
| Boilermaker (Boone, De Kalb, & Winnebago Counties) | $53.10 | $38.54 | $91.64 |
| Boilermaker (Bureau, Carroll, Fulton, Hancock, Henderson, Henry, Jo Daviess, Knox, La Salle, Lee, Livingston, Logan, Mcdonough, Mclean, Marshall, Mason, Mercer, Ogle, Putnam, Rock Island, Schuyler, Stark, Stephenson, Warren, Whiteside, And Woodford Counties) | $45.23 | $32.76 | $77.99 |
| Boilermaker (Adams, Bond, Brown, Calhoun, Cass, Clinton, Greene, Jersey, Macoupin, Menard, Monroe, Montgomery, Morgan, Pike, Randolph, And Washington Counties) | $45.50 | $35.30 | $80.80 |
| Bricklayer (Bureau, Henry, Lasalle, Livingston, Putnam, And Stark Counties) | $40.20 | $23.59 | $63.79 |
| Tile Layer (Bureau, Henry, La Salle, Livingston, Putnam, And Stark Counties) | $38.07 | $20.21 | $58.28 |
| Tile Finisher (Bureau, Henry, La Salle, Livingston, Putnam, And Stark Counties) | $35.25 | $18.00 | $53.25 |
| Bricklayer, Caulker, Cleaner, Pointer & Stonemason (Mercer And Rock Island Counties) | $29.51 | $20.35 | $49.86 |
| Bricklayer (Fulton, Henderson, Knox, Marshall, Warren, And Woodford Counties) | $35.01 | $23.14 | $58.15 |
| Bricklayer, Caulker, Cleaner, Pointer & Stonemason (Mclean County) | $30.59 | $23.19 | $53.78 |
| Marble & Tile Setter And Terrazzo Worker (Fulton, Henderson, Knox, Marshall, Mclean, Warren, And Woodford Counties) | $32.87 | $21.09 | $53.96 |
| Base Machine Men (Fulton, Henderson, Knox, Marshall, Mclean, Warren, And Woodford Counties) | $31.13 | $21.09 | $52.22 |
| Bricklayer, Caulker, Cleaner, Pointer & Stonemason (Carroll, Jo Daviess, Lee, Ogle, Stephenson, Whiteside, And Winnebago Counties) | $40.00 | $24.72 | $64.72 |
| Bricklayer, Caulker, Cleaner, Pointer & Stonemason (Boone County) | $43.80 | $27.23 | $71.03 |
| Base Machine Men (Bureau, De Witt, Henry, La Salle, Livingston, Mercer, Putnam, Rock Island And Stark Counties) | $33.90 | $15.99 | $49.89 |
| Marble, Tile & Terrazzo Finisher (Boone, Carroll, Jo Daviess, Lee, Ogle, Stephenson, Whiteside & Winnebago Counties) | $35.69 | $19.65 | $55.34 |
| Marble & Tile Setter And Terrazzo Worker (Boone, Carroll, Jo Daviess, Lee, Ogle, Stephenson, Whiteside & Winnebago Counties) | $38.52 | $21.86 | $60.38 |
| Marble & Tile Setter And Terrazzo Worker (Mercer & Rock Island Counties) | $25.78 | $19.40 | $45.18 |
| Bricklayer, Caulker, Cleaner, Pointer & Stonemason (Randolph County) | $30.79 | $21.69 | $52.48 |
| Bricklayer: Bricklayer, Marble, Terrazzo Worker, And Tile Layer (Bond, Calhoun, Clinton, Jersey, Macoupin (Staunton & Mt. Olive), Monroe, Montgomery, And Washington Counties) | $33.13 | $22.05 | $55.18 |
| Bricklayer (Adams, Brown, Cass, Greene, Hancock, Macoupin (Except Staunton & Mt. Olive), Morgan, Mcdonough, Pike, Schuyler, And Scott Counties) | $30.79 | $21.69 | $52.48 |
| Cement Mason/Plasterer (Morgan And Scott Counties) | $31.91 | $21.93 | $53.84 |
| Bricklayer, Caulker, Cleaner, Pointer & Stonemason (Logan, Mason, And Menard Counties) | $33.49 | $24.93 | $58.42 |
| Marble, Terrazzo And Tile Finisher (Adams, Brown, Cass, Greene, Hancock, Macoupin, Morgan, Mcdonough, Pike, Schuyler, And Scott Counties) | $30.70 | $18.51 | $49.21 |
| Marble & Tile Setter And Terrazzo Worker (Adams, Brown, Cass, Greene, Hancock, Macoupin, Morgan, Mcdonough, Pike, Schuyler, And Scott Counties) | $32.20 | $18.51 | $50.71 |
| Marble, Terrazzo And Tile Finisher (Logan, Mason, And Menard Counties) | $30.24 | $17.87 | $48.11 |
| Marble Setter, Terrazzo Worker & Tile Setter (Logan, Mason, And Menard Counties) | $31.74 | $17.87 | $49.61 |
| Marble Finisher, Terrazzo Finisher And Tile Finisher (Randolph County) | $29.75 | $20.23 | $49.98 |
| Bricklayer: Including Cement Mason (De Kalb County) | $46.19 | $29.74 | $75.93 |
| Carpenter: Carpenters, Lathers, Carpet, Linoleum, And Soft Tile Layers (Henderson, Henry, Mercer, And Rock Island Counties) | $34.25 | $29.53 | $63.78 |
| Carpenter (Bureau, La Salle, Marshall, Putnam, And Stark Counties) | $39.00 | $37.45 | $76.45 |
| Carpenter/Lather (Fulton And Mason Counties) | $34.30 | $29.94 | $64.24 |
| Piledriver (Knox County) | $35.30 | $29.94 | $65.24 |
| Carpenter/Lather (Knox County) | $34.30 | $29.94 | $64.24 |
| Piledriver (Woodford County) | $34.58 | $29.10 | $63.68 |
| Carpenter/Lather (Woodford County) | $33.58 | $29.10 | $62.68 |
| Piledriver | $34.57 | $29.10 | $63.67 |
| Carpenter/Lather | $33.57 | $29.10 | $62.67 |
| Piledriver (Menard County) | $33.83 | $27.45 | $61.28 |
| Carpenter/Lather (Menard County) | $32.83 | $27.45 | $60.28 |
| Piledriver (Adams County) | $32.39 | $25.99 | $58.38 |
| Carpenter/Lather (Adams County) | $31.39 | $25.99 | $57.38 |
| Piledriver (Hancock, Mcdonough, And Warren Counties) | $35.14 | $28.60 | $63.74 |
| Carpenter/Lather (Hancock, Mcdonough, And Warren Counties) | $34.14 | $28.60 | $62.74 |
| Piledriver (Macoupin And Montgomery Counties) | $34.36 | $28.60 | $62.96 |
| Carpenter/Lather (Macoupin And Montgomery Counties) | $33.36 | $28.60 | $61.96 |
| Piledriver (Logan County) | $35.10 | $28.60 | $63.70 |
| Carpenter/Lather (Logan County) | $34.10 | $28.60 | $62.70 |
| Piledriver (Brown, Cass, Greene, Morgan, Pike, Schuyler, And Scott Counties) | $34.36 | $28.60 | $62.96 |
| Carpenter/Lather (Brown, Cass, Greene, Morgan, Pike, Schuyler, And Scott Counties) | $33.36 | $28.60 | $61.96 |
| Carpet Installer: Carpet, Linoleum, Hardwood And Tile Layer (Clinton (Excluding Brookside Twp), Monroe Randolph, And Washington Counties) | $36.08 | $18.90 | $54.98 |
| Carpenter: Lather, Piledriver And Millwright (Clinton (Excluding Brookside Twp), Monroe Randolph, And Washington Counties) | $41.36 | $18.90 | $60.26 |
| Carpet Installer: Carpet, Linoleum, Hardwood, And Tile Layer (Alexander, Franklin, Hardin, Massac, Jackson, Perry, Pope, Johnson, Gallatin, Pulaski, Saline, Union, And Williamson Counties) | $36.08 | $18.90 | $54.98 |
| Carpet Installer: Carpet, Linoleum, Hardwood, And Tile Layer (Bond, Calhoun, And Jersey Counties) | $36.08 | $18.90 | $54.98 |
| Carpenter: Lather, Piledriver, And Millwright (Bond, Calhoun, And Jersey Counties) | $41.36 | $18.90 | $60.26 |
| Carpenter/Lather: Dekalb, Lee (East Of Brooklyn Road), Ogle (Territory Within Il Route 72, Meridian Road & The Southern Ogle County Line) | $50.41 | $38.53 | $88.94 |
| Carpenter/Lather: (Carroll, Jo Daviess, Lee (West Of Brooklyn Road), Ogle (Remainder Of Southern Half), Stephenson, And Whiteside) | $42.14 | $37.12 | $79.26 |
| Carpenter, Lather, Soft Floor Layer (Boone, Ogle (Northern Half), And Winnebago Counties) | $47.25 | $37.87 | $85.12 |
| Millwright (Fulton, Hancock, Knox, Logan, Mason, Mcdonough, Warren, And Woodford Counties) | $33.06 | $29.97 | $63.03 |
| Millwright (Adams, Brown, Cass, Greene, Macoupin, Menard, Montgomery, Morgan, Pike, Schuyler, And Scott Counties) | $33.06 | $29.36 | $62.42 |
| Millwright (Livingston And Mclean Counties) | $33.06 | $30.04 | $63.10 |
| Millwright: Zone 5: Bureau, Dekalb, La Salle, Lee, Marshall, Putnam, Rock Island (West), Stark, And Whiteside Counties | $51.09 | $33.61 | $84.70 |
| Millwright: Zone 3: Boone, Jo Daviess, Ogle, Stephenson, And Winnebago Counties | $51.81 | $32.69 | $84.50 |
| Millwright: Zone 1: Carroll, Henderson, Henry, Mercer, And Rock Island (East) Counties | $39.31 | $29.84 | $69.15 |
| Electrician (Peoria Division - Marshall (Area West Of Bell Plain & Roberts Twps) And Woodford (Area West Of Kansas, Linn, Palestine & Roanoke Twps) Counties) | $45.65 | $26.77 | $72.42 |
| Electrician (Galesburg Division - Fulton (Cass, Deerfield, Ellisville, Harris, Lee, Union, Young, & Hickory Twps), Henderson, Knox, Mcdonough (Blandinsville, Prairie City, Emmet, Tennessee, Scotland, Sciota, Bushnell, Chalmers Twps), Mercer (Ohio Grove, North Henderson, And Suez Twps), And Warren Counties) | $45.65 | $26.77 | $72.42 |
| Electrician (Quincy Division - Adams, Brown, Hancock, Mcdonough (Lamoine, Bethel, Industry & Eldorado), Pike, And Schuyler Counties) | $35.00 | $20.67 | $55.67 |
| Electrician (Peoria Division - Fulton (Except Cass, Deerfield, Ellisville, Harris, Lee, Union, Young, & Hickory Twps); Mason (Except Bath, Crane, Creek, Kilbourne, Lynchburg, Mason City, And Salt Creek Twps); And Stark (Essex, Valley & West Jersey Twps) Counties) | $39.50 | $24.24 | $63.74 |
| Adams, Brown, Fulton, Hancock, Henderson, Knox, Marshall Westside), Mason (Northside), Mcdonough, Mercer (Southeast Side), Peoria, Pike, Schuyler, Stark (Southside), Tazwell, Warren, Woodford (Westside) Counites) | $37.70 | $23.40 | $61.10 |
| Electrician (Carroll (Chadwick, Mt. Carroll, Savanna And Thompson Twps), Henry (Except Annawan, Burns, Cambridge, Galva, Kewanee, Weller, And Westerfield Twps), Jo Daviess (Savanna Ordanance Depot), Mercer (Except Ohio Grove, North Henderson, & Suez), Whiteside (Remainder), And Rock Island Counties) | $46.00 | $28.56 | $74.56 |
| Cable Splicer (Carroll (Chadwick, Mt. Carroll, Savanna And Thompson Twps), Henry (Except Annawan, Burns, Cambridge, Galva, Kewanee, Weller, And Westerfield Twps), Jo Daviess (Savanna Ordanance Depot), Mercer (Except Ohio Grove, North Henderson, & Suez), Whiteside (Remainder), And Rock Island Counties) | $47.00 | $28.64 | $75.64 |
| Electrician (Bureau, Henry (Anawan, Burns, Cambridge, Galva, Kewanee, Weller, And Westerfield Twps), La Salle (Deer Park, Eden, La Salle, Peru, Utica, Ottawa, Seneca & Vermilion Twps), Putnam (Granville, Hennepin & Senachwine Twps) And Stark (Elmira, Goshen, Oseola, Penn, And Toulon Twps) Counties) | $50.45 | $44.96 | $95.41 |
| Catv Installer (Bureau, Henry (Anawan, Burns, Cambridge, Calva, Kewanee, Weller, And Westerfield Twps), La Salle (Deer Park, Eden, La Salle, Peru, Utica, Ottawa, Seneca, & Vermilion Twps), Putnam (Granville, Hennepin, & Senachwine Twps), & Stark (Elmira, Goshen, Oseola, Penn, And Toulon Twps) Counties) | $37.50 | $32.78 | $70.28 |
| Electrician (Cass, Logan, Macoupin (Athenville, Scottville, Girard & Area North Thereof), Mason (Lynchburg, Bath, Kilbourne, Crane Creek, Salt Creek & Mason Twps), Menard, Montgomery (Bois D Arc, Pitman, & Harvel Twps), Morgan, And Scott Counties) | $39.80 | $23.08 | $62.88 |
| Macoupin (Northside), Mason (Southside), Menard, Morgan, Montogomery (Northwest Side), Scott, And Sangamon Counties) | $39.66 | $21.44 | $61.10 |
| Electrician (Mc Lean (Except Anchor, Belleflower, Cropsey, Cheney Grove Twps) And Woodford (Palestine, El Paso & Kansas Twps) Counties) | $43.86 | $23.72 | $67.58 |
| Western (Northside), Mclean (Southside), And Woodford (Southside) Counties) | $40.63 | $20.47 | $61.10 |
| Electrician (Bond (Western Half), Clinton (Except Huey, Hoffman, And Vicinity), Macoupin (Except Brighton Twp, Athenville, Scottville, Girard, And Area North Thereof), Monroe, Montgomery (West Of Butler Grove, Isham, & Raymond Twps), Randolph (Red Bud Twp), And Washington (Venedy Twp) Counties) | $52.41 | $30.27 | $82.68 |
| Clinton (Westside), Macoupin (Central And Southeast Sides), Madison (Southeast Side), Monroe (Westside), Montgomery (Northwest Side), Randolph, St. Clair, And Washington (Northwest Side) Counties) | $35.27 | $15.65 | $50.92 |
| Dekalb (Franklin, Kingston, Genoa, South Grove, Mansfield, Dekalb, Corland, Milan, Alton Pierce, Shabbona Mayfield, Sycamore, Malta, Paw Paw, Squaw Grove, Victor, & Somonauk Twps), Jo Daviess (Warren & Rush), Lee, Ogle, Stephenson, Whiteside (Genesee, Jordan, Hopkins, Sterling, Hume, Montgomery, Tampico, & Hahnaman Twps), And Winnebago Counties) | $62.61 | $43.96 | $106.57 |
| Electrician (De Kalb County (Sandwich Twp)) | $60.17 | $43.50 | $103.67 |
| (Southeastern Side), And Vermilion Counties) | $40.64 | $20.46 | $61.10 |
| Electrician (La Salle (Remainder), Livingston, Mclean (Cropsey, Anchor, Cheney Grove, & Belleflower Twps), Marshall (Roberts, Evans, Bell, Plaine, & Bennington), Putnam (Magnolia Twp), And Woodford (Linn, Clayton, Minonk, Roanoke, Green, & Panola Twps) Counties) | $49.63 | $22.51 | $72.14 |
| Electrician (Calhoun, Green, Jersey, And Macoupin (Brighton Twp) Counties) | $54.53 | $29.46 | $83.99 |
| Jersey, Madison (Northwest Side), Macoupin (Southwest Side) Counties) | $36.91 | $20.99 | $57.90 |
| Electrician (Bond (Eastern Half), Clinton (Huey, Hoffman, & Vicinity), Randolph (Except Red Bud Twp), And Washington (Except Venedy Twp) Counties) | $52.14 | $29.14 | $81.28 |
| A) Employer Contributes 8% Of Regular Basic Hourly Rate As As Vacation Pay Credit For Employees With More Than 5 Years Of Service, And 6% For Less Than 5 Years Of Service B) Eight Paid Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day Friday After Thanksgiving Day, Veterans' Day And Christmas Day | $62.73 | $38.44 | $101.17 |
| Employer Contributes 8% Of Regular Basic Hourly Rate As Vacation Pay Credit For Employees With More Than 5 Years Of Service, And 6% For Employees With Less Than 5 Years Of Service. B. Paid Holidays: New Year'S Day; Memorial Day; Independence Day; Labor Day; Veteran'S Day; Thanksgiving Day; Day After Thanksgiving; & Christmas Day | $56.30 | $38.44 | $94.74 |
| A. Employer Contributes 8% Of Regular Basic Hourly Rate As Vacation Pay Credit For Employees With More Than 5 Years Of Service, And 6% For Under 5 Years Of Service. B. Paid Holidays: New Year'S Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; Day After Thanksgiving; Veterans' Day & Christmas Day | $57.99 | $38.44 | $96.43 |
| Contributes 8% Of Regular Basic Hourly Rate As Vacation Pay Credit For Employees With More Than 5 Years Of Service, And 6% For Under 5 Years Of Service. B. Paid Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, Veterans' Day And Christmas Day | $65.17 | $38.44 | $103.61 |
| Units, (Pile Driving And Extracting); Lowboys; Pumps Over 3"" (1 To 3 Not To Exceed A Total Of 300 Ft); Pumps, Well Points; Welding Machines (2 Through 5); Winches, 4 Small Electric Drill Winches (Bureau (East And North Of Rt. 26), La Salle, Livingston, And Putnam (East & South Of The Illinois River) Counties) | $59.15 | $51.00 | $110.15 |
| Rock Drill (Self-Propelled); Rock Drill (Truck Mounted)*; Rollers; Steam Generators; Tractors; Tractor Drawn Vibratory Roller (Additional .50/Hr); A-Frame Winch Trucks *Requires An Oiler (Bureau (East And North Of Rt. 26), La Salle, Livingston, And Putnam (East & South Of The Illinois River) Counties) | $61.70 | $51.00 | $112.70 |
| Roto Mill Grinder 36"" And Over*; Roto Mill Grinder Less Than 36""; Scoops-Tractor Drawn; Slip-Form Paver*; Straddle Buggies; Tournapull; Tractor With Boom And Side Boom; Trenching Machines *Requires An Oiler (Bureau (East And North Of Rt. 26), La Salle, Livingston, And Putnam (East & South Of The Illinois River) Counties) | $63.00 | $51.00 | $114.00 |
| Mechanical Heater (Other Than Steam Boiler); Small Outboard Motor Boat (Safety Boat & Life Boat); Water Pump (More Than One Well Point Pump). (Henry (Western Half), Mercer, Rock Island, And Whiteside (Western Part From The 5Th Sectional Line East Of Morrison Running Directly North And South) Counties) | $37.80 | $41.25 | $79.05 |
| Capacity); Grout Pump; Light Plant; Mechanical Broom; Mud Jack; Self-Propelled Roller (Other Than Listed In Group 2); Straddle Carrier; Trench Machine (Under 40 H.P.). (Henry (Western Half), Mercer, Rock Island, And Whiteside (Western Part From The 5Th Sectional Line East Of Morrison Running Directly North And South) Counties) | $38.85 | $41.25 | $80.10 |
| Foot Compactor; Shovel; Slip Form Paver; Steel Track-Type Tractor (Dozer, Push Cat, Etc.); Transfer Or Shuttle Buggy; Trenching Machine (40 H.P. & Over); Work Boat. (Henry (Western Half), Mercer, Rock Island, And Whiteside (Western Part From The 5Th Sectional Line East Of Morrison Running Directly North And South) Counties) | $41.50 | $41.25 | $82.75 |
| Operator: Power Equipment, Group 1 Crane (Friction Or Hydraulic, Regardless Of Size Or Attachments); Tow Or Push Boat (Henry (Western Half), Mercer, Rock Island, And Whiteside (Western Part From The 5Th Sectional Line East Of Morrison Running Directly North And South) Counties) | $43.50 | $41.25 | $84.75 |
| Power Equipment Operator Group 12 Licensed Boat Pilot (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $51.70 | $39.10 | $90.80 |
| Power Equipment Operator Group 11 Master Mechanic (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $50.70 | $39.10 | $89.80 |
| Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $45.25 | $34.95 | $80.20 |
| Power Equipment Operator: Group 09 Operators On Equipment With Booms, Including Jibs, 150 Ft And Over, But Less Than 200 Ft (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $49.70 | $39.10 | $88.80 |
| Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $49.80 | $36.90 | $86.70 |
| Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $49.50 | $36.90 | $86.40 |
| Power Equipment Operator: Group 06 Operators On Equipment With Booms, Including Jibs, 100 Ft And Over, But Less Than 150 Ft (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $51.45 | $39.10 | $90.55 |
| Power Equipment Operator: Group 05 Oilers (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $43.15 | $39.10 | $82.25 |
| Power Equipment Operator: Group 04 Firemen On Whirlies And Asphalt Spreader Oiler; Heavy Equipment Oilers; Truck Cranes; Monigans; Large Over 65 Tons Capacity; Concrete Plant Oiler And Black Top Plant Oiler (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $43.15 | $39.10 | $82.25 |
| Power Equipment Operator: Group 03 Air Compressor One; Water Pump Regardless Of Size One; Welding Machine One; 1-Bag Mixer One; Conveyor One; Siphon Or Jet; Light Plant One; Heater One; Immobile Track Air One (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $43.09 | $39.10 | $82.19 |
| Power Equipment Operator: Group 02 Assistant Operators (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $47.57 | $39.10 | $86.67 |
| Regardless Of Size, Nail Launchers When Mounted On A Machine Or Self-Propelled, Con-Cover Machines, Goldhofer And Similar S.P.M.T. (Self-Propelled Modular Transpmiers) Heavy Transport Units And All Operators (Except Those Listed Below). (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $48.70 | $39.10 | $87.80 |
| Mixer (3) Bag And Under(Standard Capacity With Skip); Bulk Cement Plant; Oiler On Central Concrete Mixing Plant; Stud Welder (Bureau (West Of Rt. 26), Fulton, Hancock, Henderson, Henry (Eastern Half), Knox, Marshall, Mason, Mcdonough, Mclean, Putnam (West Of Illinois River), Stark, Warren, And Woodford Counties) | $38.03 | $43.42 | $81.45 |
| Permanently Installed Used For Hoisting Or Lowering Building Material; Construction Elevator Temporarily Installed (Bureau (West Of Rt. 26), Fulton, Hancock, Henderson, Henry (Eastern Half), Knox, Marshall, Mason, Mcdonough, Mclean, Putnam (West Of Illinois River), Stark, Warren, And Woodford Counties) | $44.09 | $43.42 | $87.51 |
| Similar Types; Off Road Trucks, Articulating End Dump Vehicles & Similar Types; Concrete & All Recycling Machines (Bureau (West Of Rt. 26), Fulton, Hancock, Henderson, Henry (Eastern Half), Knox, Marshall, Mason, Mcdonough, Mclean, Putnam (West Of Illinois River), Stark, Warren, And Woodford Counties) | $47.79 | $43.42 | $91.21 |
| Per Hour For Level A Work; Long Boom On A Stationary Crane 1.00 Per Hour Above Long Boom Scale Level A: (Highest Level Of Repiratory, Skin, And Eye Protection) Level B: (Same As Level A, But A Lower Level Of Skin Protection) Level C: (Same As Level B, But A Lower Level Of Respiratory Protection) | $42.32 | $28.75 | $71.07 |
| 2.00 Per Hour For Level A Work; Long Boom On A Stationary Crane 1.00 Per Hour Above Long Boom Scale Level A: (Highest Level Of Repiratory, Skin, And Eye Protection) Level B: (Same As Level A, But A Lower Level Of Skin Protection) Level C: (Same As Level B, But A Lower Level Of Respiratory Protection) | $34.30 | $28.75 | $63.05 |
| Per Hour For Level A Work; Long Boom On A Stationary Crane 1.00 Per Hour Above Long Boom Scale Level A: (Highest Level Of Repiratory, Skin, And Eye Protection) Level B: (Same As Level A, But A Lower Level Of Skin Protection) Level C: (Same As Level B, But A Lower Level Of Respiratory Protection) | $38.18 | $28.75 | $66.93 |
| Level A Work; Long Boom On A Stationary Crane 1.00 Per Hour Above Long Boom Scale Level A: (Highest Level Of Repiratory, Skin, And Eye Protection) Level B: (Same As Level A, But A Lower Level Of Skin Protection) Level C: (Same As Level B, But A Lower Level Of Respiratory Protection) | $40.71 | $28.75 | $69.46 |
| Ironworker (Adams (Southeastern Corner), Brown, Cass, Fulton (Southern Tip Including Marbletown, Astoria & Summun Twps), Greene (Northern Half), Logan, Macoupin (Northern Part), Mason (East Of Rt. 136), Menard, Montgomery (Except Litchfield, Hillsboro & South Thereof) Morgan, Pike, Schuyler (Eastern Half), And Scott Counties) | $36.20 | $31.35 | $67.55 |
| Ironworker (Carroll (Thompson, Savanna & Vicinity), Henry, Jo Daviess (East Dubuque, Galena, Hanover, & Vicinity), Knox (Galesburg And Area North Of The City), Mercer (Except Southwest Part), Rock Island, Warren (Includes Northwest Part), And Whiteside (Western Half) Counties) | $38.25 | $32.28 | $70.53 |
| Ironworker (Fulton (Except Marbletown, Astoria & Summun Twps), Knox (Area Southeast Of Galensburg), Livingston, Mclean (Western Half), Marshall (Southwestern Corner), Mason (West Of Rt. 136), Stark, And Woodford Counties) | $39.24 | $33.88 | $73.12 |
| Ironworker (Mclean County (Eastern Half)) | $37.71 | $29.65 | $67.36 |
| Ironworker (Bond, Calhoun, Clinton, Greene (Southern Half), Jersey, Macoupin (Southern Part), Monroe, Montgomery (Litchfield, Hillsboro & South Thereof), Randolph, And Washington Counties) | $41.65 | $31.18 | $72.83 |
| Ironworker (Dekalb County (Southeastern 2/3 Including Sycamore And Dekalb)) | $48.83 | $39.84 | $88.67 |
| Ironworker (La Salle, Marshall (Except The Southwestern Part), And Putnman Counties) | $45.50 | $38.90 | $84.40 |
| Ironworker (Boone, Carroll (Except Thompson, Savanna & Vicinity.), Dekalb (Except Southeastern 2/3), Jo Daviess (Except East Dubuque, Galena, Hanover & Vicinity), Lee, Ogle, Stephenson, Whiteside (Cities Of Rock Falls, Sterling, West Sterling), And Winnebago Counties) | $41.37 | $44.41 | $85.78 |
| Ironworker (Adams, Hancock, Henderson, Knox (West Of Hwy #41), Mc Donough, Mercer (Southwest Part), Schuyler (Western Half), And Warren (Except Northwest Part) Counties) | $36.30 | $25.80 | $62.10 |
| Asphalt Workers With Machine & Layers, Asphalt Plant Laborer, Wrecking, Fire-Proofing, Driving Stakes, Stringlines For All Machinery, Window Cleaning, Demolition Worker, Explosive Handling, Trimming & Removal Of Trees, Multi-Plate Pipe, Pilot Cars For Traffic Control, Power Rigging (Dekalb And Winnebago Counties) | $41.34 | $33.11 | $74.45 |
| Laborer Group 3 Dynamite Man (Clinton County (Northwest)) | $36.88 | $29.35 | $66.23 |
| Laborer Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Clinton County (Northwest)) | $35.88 | $29.35 | $65.23 |
| Laborer Group 1 General Laborer (Clinton County (Northwest)) | $35.38 | $29.35 | $64.73 |
| Laborer Group 8 Asbestos Abatement Laborers, Toxic And Hazardous Waste Removal Laborers, Dosimeter (Any Device) Monitoring Nuclear Exposure (Boone County) | $51.80 | $36.94 | $88.74 |
| Laborer Group 7 Caisson Laborers, Dynamiters (Boone County) | $52.10 | $36.94 | $89.04 |
| Laborer Group 6 Tile Layers, Bottom Men (Boone County) | $52.10 | $36.94 | $89.04 |
| Laborer Group 5 Jackhammer & Air Spade, Chainsaw, Swinging Stage And Boatswain Chair, Cement Gun Nozzleman, Hod Carrier, Plaster Tender, Tunnel Man, And Tree Surgeon-Topper (Boone County) | $51.75 | $36.94 | $88.69 |
| Laborer Group 4 Power Tamper (Boone County) | $51.75 | $36.94 | $88.69 |
| Laborer Group 3 Torchman (Demolition), Mortarman (Boone County) | $51.40 | $36.94 | $88.34 |
| Laborer Group 2 Power Virbrator (Boone County) | $51.75 | $36.94 | $88.69 |
| Laborer Group 1 Common Laborer, Bobcat, Forklift (Boone County) | $51.40 | $36.94 | $88.34 |
| Laborers, Group 3 Dynamite Man And Powder Man (Monroe County) | $34.31 | $31.92 | $66.23 |
| Laborers, Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Monroe County) | $33.31 | $31.92 | $65.23 |
| Laborers, Group 1 General Laborer (Monroe County) | $32.81 | $31.92 | $64.73 |
| Laborer Group 3 Dynamite Man And Powder Man (Calhoun, Greene, And Jersey Counties) | $34.34 | $27.89 | $62.23 |
| Laborer Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Calhoun, Greene, And Jersey Counties) | $33.34 | $27.89 | $61.23 |
| Laborer Group 1 General Laborer (Calhoun, Greene, And Jersey Counties) | $32.84 | $27.89 | $60.73 |
| Laborer (Hancock And Mcdonough Counties) | $33.00 | $28.34 | $61.34 |
| Asbestos Abatement Worker (Hancock And Mcdonough Counties) | $35.25 | $28.34 | $63.59 |
| Laborer (Adams County) | $31.13 | $25.06 | $56.19 |
| Asbestos Abatement Worker (Adams County) | $33.38 | $25.06 | $58.44 |
| Laborer (Building) (Brown, Mason, Pike, And Schuyler Counties) | $31.70 | $27.28 | $58.98 |
| Asbestos Abatement Worker (Building) (Brown, Mason, Pike, And Schuyler Counties) | $33.95 | $27.28 | $61.23 |
| Laborer (Fulton County) | $34.00 | $30.04 | $64.04 |
| Laborers, Group 3 Concrete Specialist (Mercer And Rock Island Counties) | $30.71 | $24.10 | $54.81 |
| Laborers, Group 2 Dynamite Man, Asbestos Abatement Worker, Hazardous Waste Abatement Work, Lead Base Paint Abatement Worker, And Unloading Explosives (Mercer And Rock Island Counties) | $30.06 | $24.10 | $54.16 |
| Operators, Paving Breakers, Air Tamping Hammerman, Concrete Saws, Concrete Burning Machine Operator, Coring Machine Operator-Hod Carrier And Plasterer Tender, Caisson Worker After 6 Foot Depth, Tunnel Miners, Mixerman (Plaster Only), Pump Man, Retaining Walls, Culvert Walls, Slope Walls, And Wing Walls (Mercer And Rock Island Counties) | $28.56 | $24.10 | $52.66 |
| Laborer Group 3 Dynamite Man And Powder Man (Macoupin County) | $35.64 | $30.59 | $66.23 |
| Laborer Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Macoupin County) | $34.64 | $30.59 | $65.23 |
| Laborer Group 1 General Laborer (Macoupin County) | $34.14 | $30.59 | $64.73 |
| Laborer: General Laborer (Mclean County) | $35.14 | $28.49 | $63.63 |
| Laborer: Asbestos Abatement Worker (Mclean County) | $37.14 | $28.49 | $65.63 |
| Laborer Group 4 Dynamite Man (Bureau, La Salle, And Putnam Counties) | $41.54 | $32.42 | $73.96 |
| Laborers Handling Masterplate Or Similar Materials; Laser Beam Operator; Coring Machine Operator; Plasterer Tenders; Underpinning And Shoring Of Building; Material Selector When Working With Firebrick Or Castable Materials; Fire Watch; Signalling Of All Power Equipment; Tree Topper Or Trimmer (Bureau, La Salle, And Putnam Counties) | $40.54 | $32.42 | $72.96 |
| Power Tools; Driving All Stakes, Stringlines For All Machinery; Setting And Building Of Manholes And Catch Basins; Stripping Of All Concrete Forms Except Paving Forms; All Concrete Paving And Slope Walls, Placing, Cutting And Tying Of Reinforcing (Re-Bars And Wire Mesh) (Bureau, La Salle, And Putnam Counties) | $40.54 | $32.42 | $72.96 |
| Laborer Group 1 Unskilled - All Classifications Not Listed Below (Bureau, La Salle, And Putnam Counties) | $40.54 | $32.42 | $72.96 |
| Laborer Group Asbestos Abatement Worker And Hazardous Waste Worker5 (Bureau, La Salle, And Putnam Counties) | $42.54 | $32.42 | $74.96 |
| Laborers, Group 3 Dynamite Man (Randolph And Washington Counties) | $35.64 | $30.59 | $66.23 |
| Laborers, Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Randolph And Washington Counties) | $34.64 | $30.59 | $65.23 |
| Laborers, Group 1 General Laborer (Randolph And Washington Counties) | $34.14 | $30.59 | $64.73 |
| Laborers: General Laborer (Menard County) | $32.90 | $29.26 | $62.16 |
| Laborers: Asbestos Abatement Worker (Menard County) | $35.90 | $29.26 | $65.16 |
| Laborer: General Laborer (Logan County) | $32.92 | $29.26 | $62.18 |
| Laborer: Asbestos Abatement Worker (Logan County) | $35.92 | $29.26 | $65.18 |
| Laborer: General Laborer (Cass, Morgan, And Scott Counties) | $30.49 | $29.26 | $59.75 |
| Laborer: Asbestos Abatement Worker (Cass, Morgan, And Scott Counties) | $33.49 | $29.26 | $62.75 |
| Laborer: General Laborer (Henderson, Henry, Knox, Warren, And Stark (West) Counties) | $35.66 | $27.80 | $63.46 |
| Laborer: Dynamite Men; Asbestos Abatement Laborer; And Hazardous Waste Worker (Henderson, Henry, Knox, Warren, And Stark (West) Counties) | $37.66 | $27.80 | $65.46 |
| Laborers, Group 3 Dynamite Man And Powder Man (Clinton County (Northeast)) | $32.50 | $33.73 | $66.23 |
| Laborers, Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker; (Clinton County (Northeast)) | $31.50 | $33.73 | $65.23 |
| Laborers, Group 1 General Laborer (Clinton County (Northeast)) | $31.00 | $33.73 | $64.73 |
| Laborers, Group 3 Dynamite Man (Bond County (Northside)) | $31.15 | $35.08 | $66.23 |
| Laborers, Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Bond County (Northside)) | $30.15 | $35.08 | $65.23 |
| Laborers, Group 1 General Laborer (Bond County (Northside)) | $29.65 | $35.08 | $64.73 |
| Laborers, Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Bond County (Except The Northside)) | $30.15 | $35.08 | $65.23 |
| Laborers, Group 1 General Laborer (Bond County (Except The Northside)) | $29.65 | $35.08 | $64.73 |
| Laborers, Group 3 Dynamite Man (Bond County (Except The Northside)) | $31.15 | $35.08 | $66.23 |
| Master Plate Or Similar Materials; Laser Beam; Concrete Burning Machine Operator; Coring Machine Operator; Plaster Tender; Underpinning And Shoring Of Buildings; Pump Men; Manhole And Catch Basin; Dirt & Stone Tamper; Hose Men On Concrete Pump. (Carroll, Jo Daviess, Lee, Ogle, Stephenson, And Whiteside Counties) | $40.47 | $34.05 | $74.52 |
| Laborers, Group 3 Dynamite Man (Clinton County (Southwest)) | $30.76 | $31.47 | $62.23 |
| Laborers, Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Clinton County (Southwest)) | $29.76 | $31.47 | $61.23 |
| Laborers, Group 1 General Laborer (Clinton County (Southwest)) | $29.26 | $31.47 | $60.73 |
| Laborer Group 2 Dynamite Men; Asbestos Abatement Laborer; Hazardous Waste Worker (Livingston, Marshall, Stark (Eastern Half), And Woodford Counties) | $38.59 | $27.04 | $65.63 |
| Laborers At The Minimum Rate That Prevails In This Agreement; Moving, Signalling, Hooking On And Unhooking, Flagging Of All Power Machines; Driving Stakes And Setting Of All Stringlines For All Electronic Devices And All Machinery. (Livingston, Marshall, Stark (Eastern Half), And Woodford Counties) | $36.59 | $27.04 | $63.63 |
| Laborers, Group 3 Dynamite Man (Bond (Sorento) And Montgomery Counties) | $33.91 | $32.32 | $66.23 |
| Laborers, Group 2 Asbestos Abatement Worker And Hazardous Waste Worker; Lead Base Paint Worker (Bond (Sorento) And Montgomery Counties) | $32.91 | $32.32 | $65.23 |
| Laborers, Group 1 General Laborer (Bond (Sorento) And Montgomery Counties) | $32.41 | $32.32 | $64.73 |
| Painter: Brush, Drywall Taper/Finisher, Sandblaster, And Spray (De Kalb, Du Page, Kane, Kendall And Mchenry Counties) | $53.05 | $27.63 | $80.68 |
| Painter: Brush, Roller, Spray, Sandblasting, Paperhanger, Drywall Finishing, Taper, And Spray Structural Steel (Boone, Jo Daviess, Lee, Ogle, Stephenson And Winnebago Counties) | $45.15 | $29.41 | $74.56 |
| Painter: Brush, Roller, Pressure Roller, Spray, Airless Spray, Sandblasting, Taper, Drywall Taper/Finisher, Structural Steel, And Bridges (Bureau, Ford, Hancock, La Salle, Livingston, Mcdonough, Mclean, Putnam And Stark Counties) | $40.00 | $26.90 | $66.90 |
| Painter (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Pike, And Washington Counties) | $31.25 | $17.12 | $48.37 |
| Painter: Brush, Spray, Pressure Roller, Sandblasting, Bridges, & New Structural Steel Work (Fulton, Marshall, Mason, Peoria, Schuyler, Tazewell And Woodford Counties) | $40.00 | $26.90 | $66.90 |
| Glazier (Bureau, Fulton, Hancock, Lee, Lasalle, Livingston, Mcdonough, Marshall, Putnam, Stark, And Woodard Counties) | $39.74 | $27.78 | $67.52 |
| Glazier (Bond, Calhoun, Clinton, Greene, Jackson, Jersey, Macoupin (Southside), Madison, Marion, Monroe, Perry, Randolph, St. Clair, And Washington Counties) | $43.32 | $25.43 | $68.75 |
| Glazier (Sector Two: Carroll, Henderson, Jo Daviess, Warren, And Whiteside Counties) | $33.37 | $21.80 | $55.17 |
| Glazier (Sector One: Henry, Knox, Mercer, And Rock Island Counties) | $35.37 | $21.80 | $57.17 |
| Glazier (Boone, De Kalb, Ogle, Stephenson, And Winnebago Counties) | $48.28 | $28.50 | $76.78 |
| Glazier (Adams, Brown, Cass, Logan, Macoupin (Northern Part), Mason, Menard, Montgomery, Morgan, Pike, Schuyler, And Scott Counties) | $39.77 | $22.73 | $62.50 |
| Painter: Spray, Structural Steel, & Sandblasting (Carroll, Henderson, Henry, Knox, Mercer, Rock Island, Warren, And Whiteside Counties) | $30.50 | $17.37 | $47.87 |
| Painter: Brush And Roller (Carroll, Henderson, Henry, Knox, Mercer, Rock Island, Warren, And Whiteside Counties) | $30.00 | $17.37 | $47.37 |
| Plasterer (Carroll, Jo Daviess, Lee, Ogle, Stephenson, And Whiteside (Except Erie And Area Southwest Thereof) Counties) | $38.98 | $36.58 | $75.56 |
| Cement Mason/Concrete Finisher (Carroll, Jo Daviess, Lee, Ogle, Stephenson, And Whiteside (Except Erie And Area Southwest Thereof) Counties) | $38.48 | $38.77 | $77.25 |
| Cement Mason/Concrete Finisher (De Kalb County) | $50.70 | $40.60 | $91.30 |
| Cement Mason And Plasterer (Bureau, La Salle, Marshall (Eastern Part Including Toluca), Putnam, And Woodford (Northeast Corner - North Of Route 116 And East Of Route 117) Counties) | $40.50 | $33.54 | $74.04 |
| Plasterer (Boone County) | $37.90 | $37.66 | $75.56 |
| Cement Mason/Concrete Finisher (Boone County) | $41.03 | $36.39 | $77.42 |
| Plasterer (Winnebago County) | $37.90 | $37.66 | $75.56 |
| Cement Mason/Concrete Finisher (Winnebago County) | $41.03 | $36.39 | $77.42 |
| Plasterer (Adams, Brown, Cass, Fulton (Except Northews Portion), Hancock, Mcdonough, Menard, Pike, And Schuyler Counties) | $35.41 | $27.31 | $62.72 |
| Cement Mason/Concrete Finisher (Adams, Brown, Cass, Fulton (Except Northews Portion), Hancock, Mcdonough, Menard, Pike, And Schuyler Counties) | $31.80 | $26.89 | $58.69 |
| Plasterer (Henderson (Northern Half), Mercer (Except Southeastern Part), And Rock Island Counties) | $34.00 | $21.76 | $55.76 |
| Plasterer (Henderson County (Southern Half)) | $28.51 | $21.93 | $50.44 |
| Plasterer (Fulton (Except Northwestern Portion), Marshall (Western Part Except Toluca), Mason, And Woodford (Northwestern Part - North Of Route 116 And West Of Route 117) Counties) | $29.41 | $26.01 | $55.42 |
| Cement Mason/Concrete Finisher (Fulton (Except Northwestern Portion), Marshall (Western Part Except Toluca), Mason, And Woodford (Northwestern Part - North Of Route 116 And West Of Route 117) Counties) | $30.52 | $25.22 | $55.74 |
| Plasterer (Livingston (Southern Half), Mclean, And Woodford (South Of Route 116) Counties) | $30.00 | $27.01 | $57.01 |
| Cement Mason/Concrete Finisher (Livingston (Southern Half), Mclean, And Woodford (South Of Route 116) Counties) | $32.12 | $22.29 | $54.41 |
| Plasterer (Henry, Livingston (Northern Part Including Pontiac), And Stark Counties) | $36.70 | $22.08 | $58.78 |
| Cement Mason/Concrete Finisher (Henry, Livingston (Northern Part Including Pontiac), And Stark Counties) | $36.70 | $22.08 | $58.78 |
| Cement Mason/Concrete Finisher (Fulton (Northwestern Part), Knox, Mercer (Southeastern Corner), And Warren Counties) | $29.14 | $20.42 | $49.56 |
| Plasterer (Fulton (Northwestern Part) And Mercer (Southeastern Corner) Counties) | $29.14 | $20.42 | $49.56 |
| Cement Mason/Concrete Finisher (Henderson (Northern Half), Mercer (Except Southeastern Part), Rock Island, And Whiteside (Erie & Area Southwest Thereof) Counties) | $33.21 | $29.43 | $62.64 |
| Plasterer (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, And Montgomery (Excluding The Towns Of Coalton, Coffen, Fillmore, Nokomis, Ohlman, Wenoah, Witt) Counties) | $37.30 | $24.75 | $62.05 |
| Cement Mason (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin, Monroe, And Montgomery (Excluding The Towns Of Coalton, Coffen, Fillmore, Nokomis, Ohlman, Wenoah, Witt) Counties) | $39.00 | $30.60 | $69.60 |
| Cement Masons & Plasterers (Randolph And Washington Counties) | $30.83 | $18.06 | $48.89 |
| Plumber/Pipefitter (Boone, Carroll (East Of Rt 78 Including Mt Carroll), Jo Daviess, Ogle, Stephenson, And Winnebago Counties) | $55.54 | $31.43 | $86.97 |
| Plumber/Pipefitter (Adams, Brown, Hancock (Western Half), Carroll (West Of Rt 78 Excluding Mt Carroll), Henderson, Henry, Knox, Lee, Mercer, Rock Island, Schuyler (Except Browning, Frederick, And Hickory Twps), Warren, And Whiteside Counties) | $46.50 | $27.80 | $74.30 |
| Plumber (Fulton, Hancock (Eastern Half), Mcdonough (Except Prairie), Marshall (South Of Rt 17), Mason (North Of Rt 136), Schuyler (Browning, Frederick & Hickory Twps), Stark, And Woodford (North Of Rt 116 To Rt 116A, And Area West Of Rt 116A To, But Excluding Goodfield) Counties) | $42.70 | $30.98 | $73.68 |
| Plumber, Pipefitter, Steamfitter (Livingston (Pontiac And South Of Rt 116 Extending East To Ford County), Mclean, And Woodford (South Of Rt 16 To Rt 116A Area East Of Rt 116A To And Including Goodfield) Counties) | $50.85 | $27.75 | $78.60 |
| & Trenton), Mcdonough (Prairie), Monroe (Hecker), Randolph (Baldwin, Red Bud, Ruma, Tilden), And Washington (Addieville, Covington, Cardes, Caspars, Damiansville, Darmstrat, Elkhorn, Johannisburg, Lively Grove, Nashville, New Menden, Oakdale, Okawville, Plum, Rentcher, Stone Church Hill & Venedy) Counties) | $47.75 | $23.42 | $71.17 |
| Plumber (Bureau, La Salle, Livingston (North Of Rt. 116 Excluding The City Of Pontiac), Marshall (North Of Rt 17 And East Of Rt. 116A), And Putnam Counties) | $60.50 | $39.02 | $99.52 |
| Plumber/Pipefitter (Randolph County (Southeastern Side)) | $52.80 | $23.95 | $76.75 |
| Plumber (Clinton (Northwestern Part Including St Rose, Frogtown, Jamestown & Keyport), Randolph (Western 1/4 Including Kellog, Modoc, Prairie, Durocker, And Roots), And Monroe (Except Hecker) Counties) | $43.75 | $21.25 | $65.00 |
| Steamfitter (Clinton (Northwestern Part Including St. Rose, Frogtown, Jamestown And Key Port), Randolph (Western 1/4 Including Kellog, Modoc, Prairie, Durocker, And Roots) And Monroe (Except Hecker) Counties) | $49.00 | $24.42 | $73.42 |
| Plumber/Pipefitter (De Kalb) | $45.76 | $26.92 | $72.68 |
| Plumber/Pipefitter (Bond, Calhoun, Greene, Jersey, Macoupin (South Of Rt 108), And Montgomery (Southwest Of Rt 127) Counties) Footnote: A. 4 Hours Paid Holiday For Christmas Eve If Holiday Falls On Monday Through Friday | $51.61 | $21.45 | $73.06 |
| Pipefitter (Bureau, La Salle, Livingston (North Of Rt. 116 Excluding The City Of Pontiac), Marshall (North Of Rt 17 And East Of Rt. 116A), And Putnam Counties) | $55.00 | $38.62 | $93.62 |
| Plumber And Steamfitter (Clinton (Eastern 1/3) And Washington (Eastern 1/2) Counties) | $45.00 | $21.54 | $66.54 |
| Roofer (Bond, Calhoun, Clinton, Greene, Jersey, Macoupin (Southern Half), Monroe, Pike (Remainder), Randolph, And Washington Counties) | $40.00 | $22.05 | $62.05 |
| Roofer (Carroll, Jo Daviess, Lee, Livingston (East Of Route 47), Ogle, Stephenson, Whiteside (Sterling And Rock Falls), And Winnebago Counties) | $50.25 | $30.43 | $80.68 |
| Roofer (Bureau, La Salle, Marshall, And Putnam Counties) | $38.50 | $27.23 | $65.73 |
| Roofer (Henderson, Henry, Knox, Mcdonough (Western Half Including Macomb), Mercer, Rock Island, Warren, And Whiteside Counties) | $38.23 | $23.88 | $62.11 |
| Roofer (Fulton, Livingston (All Towns To Rt. 47), Marshall (Camp Grove, Hallock Held, Henry Lacon, Larose, Laprairie, Pattonsburg, Sparland, Toluca, Washburn And Wilburn), Mcdonough (Adair, Bushnell, Industry, Prairie City, Bardolph, Good Hope, New Philadelphia And Walnut Grove), Mclean, Stark, And Woodford Counties) | $38.05 | $24.60 | $62.65 |
| Roofer (Adams, Brown, Cass, Hancock, Logan, Macoupin (Northern Half), Mason, Menard, Montgomery, Morgan, Pike (Northern Half), Schuyler And Scott Counties) | $36.00 | $26.36 | $62.36 |
| Sheet Metal Worker (Bureau, La Salle, Marshall, Putnam, And Stark Counties) | $50.36 | $26.88 | $77.24 |
| Sheet Metal Worker (Fulton, Mclean, Peoria, Tazwell, And Woodford Counties) | $39.50 | $33.06 | $72.56 |
| Sheet Metal Worker (Zone C: West Of Illinois Route 78 & North Of U.S. Route 30 In Jo Daviess, Carroll And Whiteside Counties) | $40.26 | $24.51 | $64.77 |
| Sheet Metal Worker (Zone A: Henry, Knox, Mcdonough, Mercer, Rock Island, Warren & Whiteside (West Of Illinois Route 78 & South Of U.S. Route 30) Counties) | $44.70 | $26.18 | $70.88 |
| Sheet Metal Worker (Adams, Calhoun, Hancock, Henderson, And Pike Counties) | $38.82 | $24.70 | $63.52 |
| Sheet Metal Worker (Brown, Cass, Logan, Mason, Menard, Morgan, Schuyler, And Scott Counties) | $38.54 | $30.37 | $68.91 |
| Sheet Metal Worker (Boone, Carroll (Eastern Half), Dekalb, Jo Daviess (East Of Hwy 78) Lee, Ogle, Stephenson, Whiteside, And Winnebago Counties) | $52.14 | $37.43 | $89.57 |
| Sheet Metal Worker (Livingston County) | $56.35 | $38.65 | $95.00 |
| Sheet Metal Worker (Bond, Clinton, Greene, Jersey, Macoupin, Monroe, Montgomery, Randolph, And Washington Counties) | $46.57 | $24.48 | $71.05 |
| Truck Driver, Group 5: Drivers Who Require Special Protective Clothing While Employed On Hazardous Waste Work. (Mclean (South Of A Straight Line From Where Route 24 Intersects The Woodford County Line In A Southeast Direction To The South Southwest Corner Of Livingston County) County) | $47.64 | $25.42 | $73.06 |
| Truck Driver, Group 4: Low Boy And Oil Distributors. (Mclean (South Of A Straight Line From Where Route 24 Intersects The Woodford County Line In A Southeast Direction To The South Southwest Corner Of Livingston County) County) | $46.54 | $25.42 | $71.96 |
| A Straight Line From Where Route 24 Intersects The Woodford County Line In A Southeast Direction To The South Southwest Corner Of Livingston County) County) | $46.15 | $25.42 | $71.57 |
| (South Of A Straight Line From Where Route 24 Intersects The Woodford County Line In A Southeast Direction To The South Southwest Corner Of Livingston County) County) | $45.88 | $25.42 | $71.30 |
| Mechanic Helpers; Greasers And Tiremen; Pick-Up Trucks When Hauling Material, Tools, Or Workers To And From And On The Job Site; And Forklifts Up To 6,000 Lb Capacity. (Mclean (South Of A Straight Line From Where Route 24 Intersects The Woodford County Line In A Southeast Direction To The South Southwest Corner Of Livingston County) County) | $45.29 | $25.42 | $70.71 |
| Truck Driver, Group 5: Drivers Who Require Special Protective Clothing While Employed On Hazardous Waste Work. (Bond, Clinton, Monroe, Randolph, Washington Counties) | $47.71 | $25.72 | $73.43 |
| Truck Driver, Group 4: Low Boy And Oil Distributors. (Bond, Clinton, Monroe, Randolph, Washington Counties) | $46.60 | $25.72 | $72.32 |
| Monroe, Randolph, Washington Counties) | $46.25 | $25.72 | $71.97 |
| Clinton, Monroe, Randolph, Washington Counties) | $45.93 | $25.72 | $71.65 |
| And Brooms, Including Those Pulled By Separate Units; Truck Driver Helper, Warehouse Employees; Mechanic Helpers; Greasers And Tiremen; Pick-Up Trucks When Hauling Material, Tools, Or Workers To And From And On The Job Site; And Forklifts Up To 6,000 Lb Capacity. (Bond, Clinton, Monroe, Randolph, Washington Counties) | $45.35 | $25.72 | $71.07 |
| Route 24 In A Southeastern Direction To The South Southwest Corner Of Livingston County), And Woodford ( | $45.37 | $0.25 | $45.62 |
| Route 24 In A Southeastern Direction To The South Southwest Corner Of Livingston County), And Woodford ( | $45.17 | $0.25 | $45.42 |
| Route 24 In A Southeastern Direction To The South Southwest Corner Of Livingston County), And Woodford ( | $44.97 | $0.25 | $45.22 |
| Direction To The South Southwest Corner Of Livingston County), And Woodf | $44.82 | $0.25 | $45.07 |
| Truck Driver: 6 Axles (Boone, Carroll (East Of Route 78/North Of Route 72), Jodaviess (East Of Route 78), Stephenson, And Winnebago Counties) Footnote: An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $48.93 | $26.70 | $75.63 |
| Truck Driver: 5 Axles (Boone, Carroll (East Of Route 78/North Of Route 72), Jodaviess (East Of Route 78), Stephenson, And Winnebago Counties) Footnote: An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $48.82 | $26.70 | $75.52 |
| Truck Driver: 4 Axles (Boone, Carroll (East Of Route 78/North Of Route 72), Jodaviess (East Of Route 78), Stephenson, And Winnebago Counties) Footnote: An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $48.62 | $26.70 | $75.32 |
| Truck Driver: 2-3 Axles (Boone, Carroll (East Of Route 78/North Of Route 72), Jodaviess (East Of Route 78), Stephenson, And Winnebago Counties) | $48.47 | $26.70 | $75.17 |
| Vacation | $45.38 | $0.30 | $45.68 |
| Vacation | $45.18 | $0.30 | $45.48 |
| Vacation | $44.98 | $0.30 | $45.28 |
| Vacation | $44.83 | $0.30 | $45.13 |
| Truck Driver, Group 5: Drivers Who Require Special Protective Clothing While Employed On Hazardous Waste Work. (Henry, Mercer, Rock Island Counties) | $47.71 | $25.72 | $73.43 |
| Truck Driver, Group 4: Low Boy And Oil Distributors. (Henry, Mercer, Rock Island Counties) | $46.60 | $25.72 | $72.32 |
| Rock Island Counties) | $46.25 | $25.72 | $71.97 |
| Mercer, Rock Island Counties) | $45.93 | $25.72 | $71.65 |
| And Brooms, Including Those Pulled By Separate Units; Truck Driver Helper, Warehouse Employees; Mechanic Helpers; Greasers And Tiremen; Pick-Up Trucks When Hauling Material, Tools, Or Workers To And From And On The Job Site; And Forklifts Up To 6,000 Lb Capacity. (Henry, Mercer, Rock Island Counties) | $45.35 | $25.72 | $71.07 |
| Truck Driver, Group 5: Drivers Who Require Special Protective Clothing While Employed On Hazardous Waste Work. (Calhoun, Greene (South Of A Direct Line That Extends East From Pike County Through Hillview/Whitehall To Macoupin County), Jersey, Macoupin, Montogomery Counties) | $47.71 | $25.72 | $73.43 |
| Truck Driver, Group 4: Low Boy And Oil Distributors. (Calhoun, Greene (South Of A Direct Line That Extends East From Pike County Through Hillview/Whitehall To Macoupin County), Jersey, Macoupin, Montogomery Counties) | $46.60 | $25.72 | $72.32 |
| (South Of A Direct Line That Extends East From Pike County Through Hillview/Whitehall To Macoupin County), Jersey, Macoupin, Montogomery Counties) | $46.25 | $25.72 | $71.97 |
| Greene (South Of A Direct Line That Extends East From Pike County Through Hillview/Whitehall To Macoupin County), Jersey, Macoupin, Montogomery Counties) | $45.93 | $25.72 | $71.65 |
| Mechanic Helpers; Greasers And Tiremen; Pick-Up Trucks When Hauling Material, Tools, Or Workers To And From And On The Job Site; And Forklifts Up To 6,000 Lb Capacity. (Calhoun, Greene (South Of A Direct Line That Extends East From Pike County Through Hillview/Whitehall To Macoupin County), Jersey, Macoupin, Montogomery Counties) | $45.35 | $25.72 | $71.07 |
| Henderson, Knowx, Marshall, Mason, Mcdonough, Stark, Warren, And Woodford (All Except Northeast Corner East Of Route 51/251 And South Of Route 24) Counties) | $44.10 | $24.27 | $68.37 |
| Hancock, Henderson, Knowx, Marshall, Mason, Mcdonough, Stark, Warren, And Woodford (All Except Northeast Corner East Of Route 51/251 And South Of Route 24) Counties) | $43.83 | $24.27 | $68.10 |
| Mechanic Helpers; Greasers And Tiremen; Pick-Up Trucks When Hauling Material, Tools, Or Workers To And From And On The Job Site; And Forklifts Up To 6,000 Lb Capacity. (Fulton, Hancock, Henderson, Knowx, Marshall, Mason, Mcdonough, Stark, Warren, And Woodford (All Except Northeast Corner East Of Route 51/251 And South Of Route 24) Counties) | $43.24 | $24.27 | $67.51 |
| Truck Driver, Group 5: Drivers Who Require Special Protective Clothing While Employed On Hazardous Waste Work. (Bureau, Carroll (West Of Route78/South Of Route 72), Jo Daviess (West Of Route 78), Lasalle, Lee (West Of Route 251), Livingston (Amity, Long Point, Nevada, Newtown Reading, & Sunbury), Putnam, Whiteside Counties) | $47.64 | $25.42 | $73.06 |
| Truck Driver, Group 4: Low Boy And Oil Distributors. (Bureau, Carroll (West Of Route78/South Of Route 72), Jo Daviess (West Of Route 78), Lasalle, Lee (West Of Route 251), Livingston (Amity, Long Point, Nevada, Newtown Reading, & Sunbury), Putnam, Whiteside Counties) | $46.54 | $25.42 | $71.96 |
| (West Of Route78/South Of Route 72), Jo Daviess (West Of Route 78), Lasalle, Lee (West Of Route 251), Livingston (Amity, Long Point, Nevada, Newtown Reading, & Sunbury), Putnam, Whiteside Counties) | $46.15 | $25.42 | $71.57 |
| Carroll (West Of Route78/South Of Route 72), Jo Daviess (West Of Route 78), Lasalle, Lee (West Of Route 251), Livingston (Amity, Long Point, Nevada, Newtown Reading, & Sunbury), Putnam, Whiteside Counties) | $45.88 | $25.42 | $71.30 |
| Trucks When Hauling Material, Tools, Or Workers To And From And On The Job Site; And Forklifts Up To 6,000 Lb Capacity. (Bureau, Carroll (West Of Route78/South Of Route 72), Jo Daviess (West Of Route 78), Lasalle, Lee (West Of Route 251), Livingston (Amity, Long Point, Nevada, Newtown Reading, & Sunbury), Putnam, Whiteside Counties) | $45.29 | $25.42 | $70.71 |
| Truck Driver, Group 5: Drivers Who Require Special Protective Clothing While Employed On Hazardous Waste Work. (Adams, Brown, Cass, Clinton, Greene (North Of A Direct Line That Extends East From Pinke County Through Hillview/Whitehall To Macoupin County) Logan, Menard, Morgan, Pike, Schyler, Scott Counties | $47.71 | $25.72 | $73.43 |
| Truck Driver, Group 4: Low Boy And Oil Distributors. (Adams, Brown, Cass, Clinton, Greene (North Of A Direct Line That Extends East From Pinke County Through Hillview/Whitehall To Macoupin County) Logan, Menard, Morgan, Pike, Schyler, Scott Counties | $46.60 | $25.72 | $72.32 |
| Cass, Clinton, Greene (North Of A Direct Line That Extends East From Pinke County Through Hillview/Whitehall To Macoupin County) Logan, Menard, Morgan, Pike, Schyler, Scott Counties) | $46.25 | $25.72 | $71.97 |
| Similar Equipment When Used For Transportation Purposes; Forklift Over 6,000 Lb.Capacity; Winch Trucks; And Four Axle Combiation Units. (Adams, Brown, Cass, Clinton, Greene (North Of A Direct Line That Extends East From Pinke County Through Hillview/Whitehall To Macoupin County) Logan, Menard, Morgan, Pike, Schyler, Scott Counties) | $45.93 | $25.72 | $71.65 |
| And From And On The Job Site; And Forklifts Up To 6,000 Lb Capacity. (Adams, Brown, Cass, Clinton, Greene (North Of A Direct Line That Extends East From Pinke County Through Hillview/Whitehall To Macoupin County) Logan, Menard, Morgan, Pike, Schyler, Scott Counties) Logan, Menard, Morgan, Pike, Schyler, Scott Counties) | $45.35 | $25.72 | $71.07 |
Always price from the wage determination attached to the solicitation (and any amendment): it is the one that applies to that contract. Rates shown are copied from the public SAM.gov documents; check the official document before you bid.