Davis-Bacon rates (construction)
Minimum pay for laborers and mechanics on federal and federally funded construction over $2,000 in Will Excludes Landscape Projects County, Illinois.
Davis-Bacon Heavy, Highway
Wage determination IL20260011, revision 2, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Carpenter: Heavy & Highway (Dupage Ane Lake Counties) | $52.01 | $38.85 | $90.86 |
| Carpenter: Building (Dupage Ane Lake Counties) | $52.01 | $38.85 | $90.86 |
| Carpenter And Piledriver (Will County) | $49.76 | $38.26 | $88.02 |
| Carpenter And Piledriver (Kane, Mchenry (North Of Hwy 52), And Kendall Counties) | $52.01 | $38.86 | $90.87 |
| Carpenter (De Kalb County) | $48.60 | $38.53 | $87.13 |
| Carpenter (Carroll, Jo Daviess, Lee, Ogle (Oregon And South Thereof), Stephenson, And Whiteside Counties) | $48.60 | $38.53 | $87.13 |
| Carpenter (Boone County) | $51.00 | $36.13 | $87.13 |
| Line Construction: Lineman And Equipment Operator (Will County) | $62.10 | $37.29 | $99.39 |
| Line Construction: Groundman (Will County) | $48.44 | $29.09 | $77.53 |
| Electrician (Kane (Northern Half) And Mchenry (All) Counties) | $59.11 | $42.23 | $101.34 |
| Electrician (Lake County) | $48.28 | $50.46 | $98.74 |
| Electrician (Will County) | $52.00 | $45.01 | $97.01 |
| Line Construction: Lineman, Substation Technician, Cable Splicing Technician, Digger Operator, Crane Operator 20 Tons And Above, And Signal Technician (Boone, Dekalb, Dupage, Kane, Kendall, Lake, And Mchenry Counties) Footnote: A. Paid Holidays: Memorial Day, Independence Day, Labor Day, And Thanksgiving Day | $59.17 | $27.12 | $86.29 |
| Line Construction: Groundman Truck Driver (Boone, Dekalb, Dupage, Kane, Kendall, Lake, And Mchenry Counties) Footnote: A. Paid Holidays: Memorial Day, Independence Day, Labor Day, And Thanksgiving Day | $39.19 | $20.32 | $59.51 |
| Line Construction: Groundman (Boone, Dekalb, Dupage, Kane, Kendall, Lake, And Mchenry Counties) Footnote: A. Paid Holidays: Memorial Day, Independence Day, Labor Day, And Thanksgiving Day | $37.81 | $19.86 | $57.67 |
| Line Construction: Equipment Operator (Boone, Dekalb, Dupage, Kane, Kendall, Lake, And Mchenry Counties) Footnote: A. Paid Holidays: Memorial Day, Independence Day, Labor Day, And Thanksgiving Day | $49.22 | $23.73 | $72.95 |
| Electrician (Boone (All) & Dekalb (Remainder) Counties) | $62.61 | $43.96 | $106.57 |
| Electrician (Dekalb (Sandwich Twp), Kane (Southern Half) & Kendall (All) Counties) | $60.17 | $43.50 | $103.67 |
| Electrician (Dupage County) | $41.00 | $43.40 | $84.40 |
| Shall Receive An Additional $.50 Per Hour. Employees Working Under Air Pressure Of 7 Pounds Or Over Shall Receive $.65 Per Hour More. Mining Machines- Boring Machines: The Crew Operating And Maintaining The Mining Machines Shall Be Compensated An Additional $.50 Per Hour. (Boone And De Kalb Counties) | $56.05 | $51.05 | $107.10 |
| Operator: Power Equipment, Group 5 Bobcats (All); Brick Forklifts; Oilers; Directional Boring (Dupage, Kane, Kendall, Lake, Mchenry, And Will Counties) | $57.80 | $51.00 | $108.80 |
| Mechanical; Hydraulic Power Unit (Pile Driving, Extracting Or Drilling); Light Plants (1 To 5); Pumps, Over 3"" (1 To 3, Not To Exceed A Total Of 300 Ft); Pumps, Well Points; Tractaire; Welding Machines (2 Through 5); Winches, 4 Small Electric Drill Winches; (Dupage, Kane, Kendall, Lake, Mchenry, And Will Counties) | $59.00 | $51.00 | $110.00 |
| Jacking Machines; Post-Hole Digger; Power Saw, Concrete, Power Driven; Pug Mills; Rollers, Other Than Asphalt; Seed And Straw Blower; Steam Generators; Stump Machine; Winch Trucks With A-Frame; Work Boats; Tamper-Form Motor Driven (Dupage, Kane, Kendall, Lake, Mchenry, And Will Counties) | $60.40 | $51.00 | $111.40 |
| Tractaire With Attachment; Traffic Barrier Transfer Machine*; Trenching Machine; Truck Mounted Concrete Pump With Boom*; Underground Boring And/Or Mining Machines 5 Ft In Diameter And Over Tunnel, Etc.*; Wheel Excavator* & Widener (Apsco); Raised Or Blind Hoe Drill, Tunnel & Shaft* (Dupage, Kane, Kendall, Lake, Mchenry, And Will Counties) | $63.00 | $51.00 | $114.00 |
| Ironworker: Structural And Reinforcing (Du Page (Eastern 1/4), Lake, And Mchenry (Hebron, Woodstock, And East Thereof) Counties) | $62.46 | $46.58 | $109.04 |
| Ironworker: Sheeter (Du Page (Eastern 1/4), Lake, And Mchenry (Hebron, Woodstock, And East Thereof) Counties) | $62.71 | $46.58 | $109.29 |
| Ironworker, Ornamental (Lake, Dupage (Eastern 1/4) And Mchenry (Hebron, Woodstock & East Thereof) Counties) | $59.26 | $44.81 | $104.07 |
| Ironworker (Kendall (Southern Part) And Will Counties) | $47.80 | $42.50 | $90.30 |
| Ironworker (Boone, Dekalb (Except Southeast), And Mchenry (Northwest) Counties) | $41.37 | $44.41 | $85.78 |
| Laborer, Sewer Construction: Group 5 Asbestos Abatement Laborers, Toxic And Hazardous Waste Removal Laborers & Dosimeter Use (Any Device) Monitoring Nuclear Exposure. (Dupage County) | $51.40 | $36.94 | $88.34 |
| Laborer, Sewer Construction: Group 4 Bottom Men; Bracers-Bracing; Bricklayer'S Tender; Catch Basin Digger; Drainlayer; Dynamiter; Form Men; Jackhammermen; Powerpac; Pipelayers; Rodders; Welders & Burners; Well Point System Men. (Dupage County) | $51.75 | $36.94 | $88.69 |
| Laborer, Sewer Construction: Group 3 Cement Carriers; Cement Mixers; Concrete Repairmen; Mortar Men; Scaffold Men; And Second Bottom Men. (Dupage County) | $51.63 | $36.94 | $88.57 |
| Laborer, Sewer Construction: Group 2 Concrete Laborers; Steel Setters. (Dupage County) | $51.53 | $36.94 | $88.47 |
| Laborer, Sewer Construction: Group 1 Signalmen Top Laborers, And All Other Laborers Not Mentioned. (Dupage County) | $51.40 | $36.94 | $88.34 |
| Laborer, Tunnel: Group 5 Asbestos Abatement Laborer; Toxic And Hazardous Waste Removal Laborer; Dosimeter (Any Device) Monitoring Nuclear Exposure (Dupage County) | $51.40 | $36.94 | $88.34 |
| Operator; Drillers; Dynamiters; Erector Operator; Form Men; Jackhammermen; Powerpac; Mining Machine Operators; Mucking Machine Operator; Laser Beam Operator; Liner Plate And Ring Setters; Shield Drivers; Power Knife Operator; Welder- Burners; Pipe Jacking Machine Operator; Skinners; Maintenance Technician (Dupage County) | $51.75 | $36.94 | $88.69 |
| Laborer, Tunnel: Group 3 Concrete Repairmen; Lock Tenders (Pressure Side); Mortar Men; Muckers; Grout Machine Operators; Track Layers (Dupage County) | $51.63 | $36.94 | $88.57 |
| Laborer, Tunnel: Group 2 Air Hoist Operator; Key Board Operator; Concrete Laborer; Grout; Lock Tenders (Free Air Side); Steel Setters; Tuggers; Switchmen; Car Pusher (Dupage County) | $51.53 | $36.94 | $88.47 |
| Laborer, Tunnel: Group 1 Cage Tenders; Dumpmen; Flagmen; Signalmen; Top Laborers (Dupage County) | $51.40 | $36.94 | $88.34 |
| Laborer, Compressed Air: 34 Lbs And Over (Du Page County) | $55.40 | $36.94 | $92.34 |
| Laborer, Compressed Air, 27-33 Lbs (Du Page County) | $54.40 | $36.94 | $91.34 |
| Laborer, Compressed Air, 21-26 Lbs (Du Page County) | $53.40 | $36.94 | $90.34 |
| Laborer, Compressed Air, 16-20 Lbs (Du Page County) | $52.90 | $36.94 | $89.84 |
| Laborer, Compressed Air, 0-15 Lbs (Du Page County) | $52.40 | $36.94 | $89.34 |
| Portable Or Temporart Plant, Laborer Handling Masterplate Or Similar Materials, Laser Beam Operator, Concrete Burning Machine Operator, Coring Machine Operator, Plaster Tender, Underpinning & Shoring Of Buildings, Pump Man, Manhole & Catch Basin, Dirt & Stone Tamper, Hoseman On Concrete Pump. (De Kalb County) | $50.39 | $36.31 | $86.70 |
| Of Sod, Planting Of Trees, Asphalt Workers With Machine & Layers, Asphalt Plant Laborer, Wrecking, Fire-Proofing, Driving Stakes, Stringlines For All Machinery, Window Cleaning, Demolition Worker, Explosive Handling, Trimming & Removal Of Trees, Multi-Plate Pipe, Pilot Cars For Traffic Control, Power Rigging (De Kalb County) | $47.04 | $36.31 | $83.35 |
| Laborer Group 7 Dosimeter (Any Device) Used For Monitoring Nuclear Exposure; Asbestos Abatement Worker; Toxic And Hazardous Waste Removal Laborer; And Chimney And Silo Laborers For Every Additional 50 Feet Or Any Part Thereof Above 100 Feet High (Will County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 6 All Underground Cavern Laborers; Caisson Laborers 50 Feet Or More Below Ground Level; Laborers Working Under Radio Active Conditions (Suiting Up); Blasting Men (Powdermen) (Will County) | $51.75 | $36.94 | $88.69 |
| Laborer Group 5 Gunnite Nozzle Men; Caisson Laborers And All Tamping Hammers From 150 Lbs And Over; From 15 Feet Below Ground Level Down To 50 Feet; And All Laborers Working Inside Of A Sphere Or Any Type Of Tank For Every Additional 50 Feet Or Part Thereof Above 100 Feet In Height (Will County) | $51.60 | $36.94 | $88.54 |
| Feet; All Tamping Hammers Over 150 Lbs.; All Laborers Working Inside Of A Sphere Or Any Type Or Make Of Tank At A Height Of 48 Feet To 100 Feet; All Hydraulic, Electric And Air Tools Or Any Other Type 8 Feet Or More Below Ground Level; Vibrators-Any Type-8 Feet Or More Below Ground Level (Will County) | $51.75 | $36.94 | $88.69 |
| Setters On Roads, Highways, Streets, Airport Runaways, And Radii (Any Type Of Form) Stringline Men For All Aforementioned Work; Wagon And Tower Drillers On Land And Floating Plant Used On Dredging; Asphalt Gunners And Plug Men (Undercoating On Road Work); Mortar Pump Laborers; Plaster Pump Laborers (Will County) | $51.40 | $36.94 | $88.34 |
| Laborer Group 2 Sewer And Drain Pipe Layers And Multiple Concrete Duct Or Any Other Type Of Pipe Used, On Public Utility Work (Ground Level To 8 Feet); Pumpcrete Pipe Handlers (Will County) | $51.75 | $36.94 | $88.69 |
| Dredgehand; Shore Laborer; Bankmen On Floating Plant; Tool And Material Checkers; Signalmen And Flagmen On All Construction Work; Cleaning Of Debris; Removal Of Trees; Concrete Curing, Temporary Concrete Protection Regardless Of Manner Or Materials Used; Laborers On Apsco; Janitorial; Wrecking And Demolition Laborers (Will County) | $51.40 | $36.94 | $88.34 |
| Laborer Group 9 Asbestos Apatement Laborers, Toxic & Hazardous Waste Removal Laborers & Dosimeter (Any Device) Monitoring Nuclear Exposure (Boone, Kane, Kendall, And Mchenry Counties) | $52.40 | $36.94 | $89.34 |
| Laborer Group 8 Flagman (Boone, Kane, Kendall, And Mchenry Counties) | $51.40 | $36.94 | $88.34 |
| Laborer Group 7 Caisson Diggers, Dynamiters (Boone, Kane, Kendall, And Mchenry Counties) | $51.75 | $36.94 | $88.69 |
| Laborer Group 6 Tunnel Laborers, Tile Layers & Bottom Men (Boone, Kane, Kendall, And Mchenry Counties) | $51.75 | $36.94 | $88.69 |
| Laborer Group 5 Chain Saw Man, Jackhammer Man, Drillman, Concrete Breaders & Air Spade (Boone, Kane, Kendall, And Mchenry Counties) | $51.63 | $36.94 | $88.57 |
| Laborer Group 4 Stringline & Form Setter; Torchman (Demolition), Sheeting & Cribbing, Black Top Rakers & Lutemen, Machine Screwmen (Boone, Kane, Kendall, And Mchenry Counties) | $51.68 | $36.94 | $88.62 |
| Laborer Group 3 Mortar & Concrete Mixers (Boone, Kane, Kendall, And Mchenry Counties) | $51.68 | $36.94 | $88.62 |
| Laborer Group 2 Air Tampers & Vibrators (Boone, Kane, Kendall, And Mchenry Counties) | $51.68 | $36.94 | $88.62 |
| Laborer Group 1 Common Laborer, Asphalt Laborer, Asphalt Plant Laborer, Striping Laborer, Clipper Type Concrete Saw, Self-Propelled Saws (Boone, Kane, Kendall, And Mchenry Counties) | $51.40 | $36.94 | $88.34 |
| Laborer Group 6 Asbestos Abatement Laborers; Toxic And Hazardous Waste Removal Laborers; Dosimeter (Any Device Monitoring Nuclear Exposure) (Lake County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 5 Cement Gun Nozzle (Gunite) (Lake County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 4 Rakers And Lutemen; Machine Screwman; Kettlemen; Mixermen, Drum-Men; Jackhammermen (Asphalt); Mite Box Spreaders; Laborers On Birch Overman And Similar Spreader Equipment; Laborers On Apsco; Laborers On Air Compressors; Paving Form Setters; Jackhammerman (Concrete); Power Drive Concrete Saws (Lake County) | $51.63 | $36.94 | $88.57 |
| Laborer Group 3 Asphalt Tampers And Smoothers (Lake County) | $51.40 | $36.94 | $88.34 |
| Laborer Group 2 Cement Gun Laborers (Lake County) | $51.48 | $36.94 | $88.42 |
| Laborer Group 1 General Laborers; Asphalt (Lake County) | $51.40 | $36.94 | $88.34 |
| Painter: Brush Only (Lake And Will Counties) | $53.05 | $33.91 | $86.96 |
| Painter: Brush, Drywall Taper/Finisher, Sandblaster, And Spray (De Kalb, Du Page, Kane, Kendall And Mchenry Counties) | $53.05 | $27.63 | $80.68 |
| Painter: Brush, Roller, Spray, Sandblasting, Paperhanger, Drywall Finishing, Taper, And Spray Structural Steel (Boone, Jo Daviess, Lee, Ogle, Stephenson And Winnebago Counties) | $45.15 | $29.41 | $74.56 |
| Cement Mason/Concrete Finisher (Will County) | $46.25 | $45.10 | $91.35 |
| Cement Mason/Concrete Finisher (De Kalb, Kane, Kendall, And Mchenry Counties) | $50.70 | $40.60 | $91.30 |
| Cement Mason/Concrete Finisher (Lake County) | $48.50 | $42.82 | $91.32 |
| Plasterer (Boone County) | $37.90 | $37.66 | $75.56 |
| Cement Mason/Concrete Finisher (Boone County) | $41.03 | $36.39 | $77.42 |
| Cement Mason/Concrete Finisher (Dupage County) | $38.00 | $24.03 | $62.03 |
| Truck Driver: 6 Axle Trucks (Kendall And Will Counties) Footnotes: A.Health And Welfare $448.80 Per Week; Pension $562.80 Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.67 | $0.30 | $46.97 |
| Truck Driver: 5 Axle Trucks (Kendall And Will Counties) Footnotes: A.Health And Welfare $448.80 Per Week; Pension $562.80 Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.47 | $0.30 | $46.77 |
| Truck Driver: 4 Axle Trucks (Kendall And Will Counties) Footnotes: A.Health And Welfare $448.80 Per Week; Pension $562.80 Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.27 | $0.30 | $46.57 |
| Truck Driver: 2 Or 3 Axle Trucks (Kendall And Will Counties) Footnotes: A.Health And Welfare $448.80 Per Week; Pension $562.80 Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.12 | $0.30 | $46.42 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $45.09 | $13.40 | $58.49 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.89 | $13.40 | $58.29 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.69 | $13.40 | $58.09 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.54 | $13.40 | $57.94 |
| Truck Driver: 6 Axles (Boone And Winnebago Counties) Footnote: An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $48.93 | $26.70 | $75.63 |
| Truck Driver: 5 Axles (Boone And Winnebago Counties) Footnote: An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $48.82 | $26.70 | $75.52 |
| Truck Driver: 4 Axles (Boone And Winnebago Counties) Footnote: An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $48.62 | $26.70 | $75.32 |
| Truck Driver: 2 - 3 Axles (Boone And Winnebago Counties) Footnote: An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $48.47 | $26.70 | $75.17 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $45.38 | $0.30 | $45.68 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $45.18 | $0.30 | $45.48 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.98 | $0.30 | $45.28 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.83 | $0.30 | $45.13 |
| Vacation | $45.86 | $0.30 | $46.16 |
| Vacation | $45.66 | $0.30 | $45.96 |
| Vacation | $45.46 | $0.30 | $45.76 |
| Vacation | $45.31 | $0.30 | $45.61 |
| To The Delivery, Maintenance And Pick-Up Of Traffic Control Devices, The Set-Up And Installation Of Traffic Signs, Pavement Markings, Barricades, Crash Barrels And Glare Screens, Traffic Control Surveillance, The Repair And Maintenance Trucks, Cars, Arrow Boards, Message Signs, Barricade And Sign Fabrication Equipment) | $43.40 | $22.71 | $66.11 |
Davis-Bacon Building, Residential
Wage determination IL20260008, revision 3, updated 1. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Hazardous Material Handler (Includes Preparation, Wetting, Stripping, Removal, Scrapping Vacuuming, Bagging And Disposing Of All Insulation Materials From Mechanical Systems, Whether They Contain Asbestos Or Not) | $41.27 | $32.76 | $74.03 |
| Fire Stop Technician | $44.02 | $32.76 | $76.78 |
| Asbestos Worker/Insulator (Includes The Application Of All Insulating Materials, Protective Coverings, Coatings, And Finishes To All Types Of Mechanical Systems) | $55.02 | $35.75 | $90.77 |
| Boilermaker (Du Page, Grundy, Kane, Kendall, Lake, Mchenry, And Will Counties) | $53.10 | $38.54 | $91.64 |
| Bricklayer (Du Page, Grundy, Lake, And Will Counties) | $48.56 | $34.05 | $82.61 |
| Marble Setter | $47.71 | $33.20 | $80.91 |
| Tile Setter | $49.75 | $30.79 | $80.54 |
| Tile Finisher | $42.80 | $26.97 | $69.77 |
| Terrazzo Worker/Setter | $48.38 | $30.79 | $79.17 |
| Marble Finisher | $33.95 | $26.03 | $59.98 |
| Bricklayer (Kane, Kendall, And Mchenry Counties) | $44.88 | $26.62 | $71.50 |
| Carpenter: Heavy & Highway (Dupage Ane Lake Counties) | $52.01 | $38.85 | $90.86 |
| Carpenter: Building (Dupage Ane Lake Counties) | $52.01 | $38.85 | $90.86 |
| Carpenter: Residential (Du Page And Lake Counties) | $45.61 | $35.31 | $80.92 |
| Carpenter; Millwright; Piledrivermen (Will County Building) | $52.01 | $41.41 | $93.42 |
| Carpenter (Will County Residential) | $45.61 | $35.31 | $80.92 |
| Carpenter: Carpenter, Floor Layer, Lather, Millwright, And Piledriver (Kane, Kendall, And Mchenry Counties Building) | $52.01 | $38.86 | $90.87 |
| Carpenter (Kane, Kendall, And Mchenry Counties Residential) | $45.61 | $35.31 | $80.92 |
| Carpenter, Carpenter, Millwright, Piledriver, And Soft Floor Layer (Grundy County) | $45.61 | $35.31 | $80.92 |
| Line Construction: Lineman And Equipment Operator (Will County) | $62.10 | $37.29 | $99.39 |
| Line Construction: Groundman (Will County) | $48.44 | $29.09 | $77.53 |
| Electrician: Building (Kane (Northern Half) And Mchenry Counties) | $59.11 | $42.23 | $101.34 |
| Interconnect, Terminal Equipment, Central Office, Pabx And Equipment, Micro Waves, V-Sat, Bypass, Catv, Wan, (Wide Area Networks), Lan (Local Area Networks), And Isdn (Integrated System Digital Network).The Work Shall Cover The Pulling Of Wire In Raceways, But Not The Installation Of Raceways. Kane (Northern Half), And Mchenry Counties) | $48.71 | $35.87 | $84.58 |
| Electrician: Residential (Kane (Northern Half) And Mchenry Counties) | $44.40 | $34.59 | $78.99 |
| Electrician: Building (Lake County) | $51.87 | $51.77 | $103.64 |
| Interconnect, Terminal Equipment, Central Office, Pabx And Equipment, Micro Waves, V-Sat, Bypass, Catv, Wan, (Wide Area Networks), Lan (Local Area Networks), And Isdn (Integrated System Digital Network).The Work Shall Cover The Pulling Of Wire In Raceways, But Not The Installation Of Raceways. (Lake County) | $48.00 | $39.85 | $87.85 |
| Electrician: Residential (Grundy And Will Counties) | $46.87 | $33.38 | $80.25 |
| Electrician: Building (Grundy And Will Counties) | $52.00 | $45.01 | $97.01 |
| Interconnect, Terminal Equipment, Central Office, Pabx And Equipment, Micro Waves, V-Sat, Bypass, Catv, Wan, (Wide Area Networks), Lan (Local Area Networks), And Isdn (Integrated System Digital Network).The Work Shall Cover The Pulling Of Wire In Raceways, But Not The Installation Of Raceways. (Grundy And Will Counties) | $44.00 | $37.91 | $81.91 |
| Electrician: Building (Kane (Southern Half) And Kendall Counties) | $60.17 | $43.50 | $103.67 |
| Interconnect, Terminal Equipment, Central Office, Pabx And Equipment, Micro Waves, V-Sat, Bypass, Catv, Wan, (Wide Area Networks), Lan (Local Area Networks), And Isdn (Integrated System Digital Network).The Work Shall Cover The Pulling Of Wire In Raceways, But Not The Installation Of Raceways. (Kane (Southern Half), And Kendall Counties) | $49.70 | $38.45 | $88.15 |
| Electrician: Residential (Dupage County) | $39.60 | $32.25 | $71.85 |
| Interconnect, Terminal Equipment, Central Office, Pabx And Equipment, Micro Waves, V-Sat, Bypass, Catv, Wan, (Wide Area Networks), Lan (Local Area Networks), And Isdn (Integrated System Digital Network).The Work Shall Cover The Pulling Of Wire In Raceways, But Not The Installation Of Raceways. (Du Page County) | $40.90 | $44.32 | $85.22 |
| Holidays: New Year'S Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; Day After Thanksgiving Day; Veterans' Day And Christmas Day. B) Employer Contributes 8% Of Regular Hourly Rate As Vacation Pay Credit For Employee With More Than 5 Years Of Service, And 6% For Employee With Less Than 5 Years Service | $70.68 | $38.44 | $109.12 |
| A. Employer Contributes 8% Of Regular Basic Hourly Rate As Vacation Pay Credit For Employees With More Than 5 Years Of Service, And 6% For Under 5 Years Of Service. B. Paid Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, Veterans' Day And Christmas Day | $61.96 | $38.44 | $100.40 |
| A. Employer Contributes 8% Of Regular Basic Hourly Rate As Vacation Pay Credit For Employees With More Than 5 Years Of Service, And 6% For Under 5 Years Of Service. B. Paid Holidays: New Year'S Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; Day After Thanksgiving; Veterans' Day & Christmas Day | $57.99 | $38.44 | $96.43 |
| Operator: Power Equipment, Group 4 (Building And Residential) Bobcats And/Or Other Skid Steer Loaders; Brick Forklifts; Oilers | $63.20 | $53.05 | $116.25 |
| Mechanical; Hoists, Inside Elevators (Remodeling Or Renovatin Work); Hydrualic Power Units (Pile Driving, Extracting, And Drilling); Low Boys; Pumps Over 3"" (1 To 3 Not To Exceed A Total Of 300 Ft); Pumps, Well Points; Welding Machines (2 Through 5); Winches, 4 Small Electric Drill Winches; Bobcat (Up To And Including 3/4 Cu Yd) | $64.95 | $53.05 | $118.00 |
| Hoists, Sewer Dragging Machine; Hoists, Tugger Single Drum; Laser Screed; Rock Drill (Self-Propelled); Rock Drill (Truck Mounted)*; Rollers; Steam Generators; Tractors; Tractor Drawn Vibratory Roller (Receives An Additional $.50 Per Hour); Winch Trucks With ""A"" Frame. *-Requires Oiler | $67.50 | $53.05 | $120.55 |
| Ironworker: Structural And Reinforcing (Du Page (Eastern 1/4), Lake, And Mchenry (Hebron, Woodstock, And East Thereof) Counties) | $62.46 | $46.58 | $109.04 |
| Ironworker: Sheeter (Du Page (Eastern 1/4), Lake, And Mchenry (Hebron, Woodstock, And East Thereof) Counties) | $62.71 | $46.58 | $109.29 |
| Ironworker, Ornamental (Lake, Dupage (Eastern 1/4) And Mchenry (Hebron, Woodstock & East Thereof) Counties) | $59.26 | $44.81 | $104.07 |
| Ironworker: Fence Erector (Lake, Dupage (Eastern 1/4), And Mchenry (Hebron, Woodstock & East Thereof) Counties) | $52.25 | $34.31 | $86.56 |
| Ironworker: Master Riggers (Lake, Dupage (Eastern 1/4) And Mchenry (Hebron, Woodstock & East Thereof) Counties) | $56.75 | $47.38 | $104.13 |
| Ironworker: Machinery Movers; Riggers; Machinery Erectors (Lake, Dupage (Eastern 1/4) And Mchenry (Hebron, Woodstock & East Thereof) Counties) | $54.25 | $47.38 | $101.63 |
| Ironworker (Dupage (Remainder), Kane, Kendall (Northern Part), And Mchenry (Southeast 1/4) Counties) | $48.83 | $39.84 | $88.67 |
| Ironworker (Dupage (Argonne & Vic), Grundy, Kendall (Southern Part), And Will Counties) | $47.80 | $42.50 | $90.30 |
| Ironworker (Mchenry County (Northwest Part)) | $41.37 | $44.41 | $85.78 |
| Laborer Group 12 Dosimeter (Any Device) Monitoring Nuclear Exposure); Asbestos Abatement Laborers; Toxic And Hazardous Waste Removal Laborers (Du Page County) | $52.40 | $36.94 | $89.34 |
| Laborer Group 11 Jackhammermen On Fire Brick Work Only (Du Page County) | $51.68 | $36.94 | $88.62 |
| Laborer Group 10 Boiler Setter Plastic Laborers (Du Page County) | $51.85 | $36.94 | $88.79 |
| Laborer Group 9 Chimney On Fire Brick; Caisson Diggers; Well Point System Men (Du Page County) | $51.75 | $36.94 | $88.69 |
| Laborer Group 8 Firebrick & Boiler Laborers (Du Page County) | $51.73 | $36.94 | $88.67 |
| Laborer Group 7 Jackhammermen, Power Driven Concrete Saws And Other Power Equipment (Du Page County) | $51.63 | $36.94 | $88.57 |
| Laborer Group 6 Stone Derrickmen And Handlers (Du Page County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 5 Cement Gun Nozzle (Gunite) Laborers; Windlass And Capstan Person (Du Page County) | $51.55 | $36.94 | $88.49 |
| Laborer Group 4 Chimney Over 40 Feet; Scaffold Laborers; Weldman-Wreckers Burners (Du Page County) | $51.50 | $36.94 | $88.44 |
| Laborer Group 3 Cement Gun Laborers And Hose (Du Page County) | $51.48 | $36.94 | $88.42 |
| Laborer Group 2 Fireproofing And Fire Shop Laborers (Du Page County) | $51.40 | $36.94 | $88.34 |
| Laborer Group 1 Building Laborers, Plasterer Tenders, Pumps For Dewatering & Other Unclassified Laborers (Du Page County) | $51.40 | $36.94 | $88.34 |
| Laborer Group 7 Dosimeter (Any Device) Used For Monitoring Nuclear Exposure; Asbestos Abatement Worker; Toxic And Hazardous Waste Removal Laborer; And Chimney And Silo Laborers For Every Additional 50 Feet Or Any Part Thereof Above 100 Feet High (Grundy And Will Counties) | $47.60 | $33.16 | $80.76 |
| Laborer Group 6 All Underground Cavern Laborers; Caisson Laborers 50 Feet Or More Below Ground Level; Laborers Working Under Radio Active Conditions (Suiting Up); Blasting Men (Powdermen) (Grundy And Will Counties) | $47.75 | $33.16 | $80.91 |
| Laborer Group 5 Gunnite Nozzle Men; Caisson Laborers And All Tamping Hammers From 150 Lbs And Over; From 15 Feet Below Ground Level Down To 50 Feet; And All Laborers Working Inside Of A Sphere Or Any Type Of Tank For Every Additional 50 Feet Or Part Thereof Above 100 Feet In Height (Grundy And Will Counties) | $47.60 | $33.16 | $80.76 |
| Feet; All Tamping Hammers Over 150 Lbs.; All Laborers Working Inside Of A Sphere Or Any Type Or Make Of Tank At A Height Of 48 Feet To 100 Feet; All Hydraulic, Electric And Air Tools Or Any Other Type 8 Feet Or More Below Ground Level; Vibrators-Any Type-8 Feet Or More Below Ground Level (Grundy And Will Counties) | $47.60 | $33.16 | $80.76 |
| Setters On Roads, Highways, Streets, Airport Runaways, And Radii (Any Type Of Form) Stringline Men For All Aforementioned Work; Wagon And Tower Drillers On Land And Floating Plant Used On Dredging; Asphalt Gunners And Plug Men (Undercoating On Road Work); Mortar Pump Laborers; Plaster Pump Laborers (Grundy And Will Counties) | $47.48 | $33.16 | $80.64 |
| Laborer Group 2 Sewer And Drain Pipe Layers And Multiple Concrete Duct Or Any Other Type Of Pipe Used, On Public Utility Work (Ground Level To 8 Feet); Pumpcrete Pipe Handlers (Grundy And Will Counties) | $47.40 | $33.16 | $80.56 |
| Plant; Tool And Material Checkers; Signalmen And Flagmen On All Construction Work; Cleaning Of Debris; Removal Of Trees; Concrete Curing, Temporary Concrete Protection Regardless Of Manner Or Materials Used; Laborers On Apsco; Janitorial; Wrecking And Demolition Laborers (Grundy And Will Counties) | $47.40 | $33.16 | $80.56 |
| Laborer: Group 2 Power Vibrator Kane, Kendall, And Mchenry Counties | $51.65 | $36.94 | $88.59 |
| Laborer: Group 1 Common Laborer Kane, Kendall, And Mchenry Counties | $51.40 | $36.94 | $88.34 |
| Laborer Group 8 Asbestos Abatement Laborers, Toxic And Hazardous Waste Removal Laborers, Dosimeter (Any Device) Monitoring Nuclear Exposureane Kendall, And Mchenry Counties | $51.80 | $36.94 | $88.74 |
| Laborer Group 7 Caisson Laborers; Dynamiters Kane, Kendall, And Mchenry Counties | $52.10 | $36.94 | $89.04 |
| Laborer Group 6 Tile Layers; Bottom Men Kane, Kendall, And Mchenry Counties | $52.10 | $36.94 | $89.04 |
| Laborer Group 5 Jackhammer & Airspade; Chainsaw, Swinging Stage And Boatswain Chair; Cement Gun Nozzleman; Hod Carrier; Plasterer Tender, And Tunnel Man Kane, Kendall, And Mchenry Counties | $51.65 | $36.94 | $88.59 |
| Laborer Group 4 Power Tamper Kane, Kendall, And Mchenry Counties | $51.65 | $36.94 | $88.59 |
| Laborer Group 3 Torchman (Demolition Only), Mortarmen Kane, Kendall, And Mchenry Counties | $51.40 | $36.94 | $88.34 |
| Laborer Group 11 Dosimeter (Any Device) Monitoring Nuclear Exposure; Asbestos Abatement Laborers; Toxic And Hazardous Waste Removal Laborers (Lake County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 10 Boiler Setter Plastic Laborers (Lake County) | $51.95 | $36.94 | $88.89 |
| Laborer Group 9 Windlass And Capstan Persons (Lake County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 8 Chimney Laborers (On Fire Brick); Caisson Diggers; Well Point System Men (Lake County) | $51.75 | $36.94 | $88.69 |
| Laborer Group 7 Firebrick & Boiler Laborer Setters (Lake County) | $51.73 | $36.94 | $88.67 |
| Laborer Group 6 Jackhammermen (Tampers & Vibrators); Power Driven Concrete Saws (Lake County) | $51.63 | $36.94 | $88.57 |
| Laborer Group 5 Stone Derrickmen And Handlers (Lake County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 4 Cement Gun Nozzle (Gunite) Laborers (Lake County) | $51.60 | $36.94 | $88.54 |
| Laborer Group 3 Chimney Over 40 Feet; Scaffold Laborers; Wall Men Or Wreckers (Lake County) | $51.50 | $36.94 | $88.44 |
| Laborer Group 2 Cement Gun Laborers And Hose (Lake County) | $51.48 | $36.94 | $88.42 |
| Laborer Group 1 Building Laborers; Plasterer Tenders, General Laborers (Wrecking And Demolition); Fireproofing And Fire Shop Laborers (Lake County) | $51.40 | $36.94 | $88.34 |
| Painter: Brush, Decorator, And Paperhanger (Grundy, Lake, And Will Counties) | $53.05 | $33.91 | $86.96 |
| Glazier | $51.55 | $44.09 | $95.64 |
| Painter: Brush, Drywall Taper/Finisher, Sandblaster, And Spray (De Kalb, Du Page, Kane, Kendall And Mchenry Counties) | $53.05 | $27.63 | $80.68 |
| Plasterer (Grundy And Will Counties) | $42.25 | $26.65 | $68.90 |
| Plasterer (Du Page County) | $42.25 | $26.65 | $68.90 |
| Cement Mason/Concrete Finisher (De Kalb, Kane, Kendall, And Mchenry Counties) | $50.70 | $40.60 | $91.30 |
| Cement Mason/Concrete Finisher (Grundy And Will Counties) | $46.25 | $45.10 | $91.35 |
| Plasterer (Lake County) | $49.65 | $42.17 | $91.82 |
| Cement Mason/Concrete Finisher (Lake County) | $48.50 | $42.82 | $91.32 |
| Cement Mason/Concrete Finisher (Dupage County) | $38.00 | $24.03 | $62.03 |
| Plumber (Lake And Mchenry Counties) | $45.76 | $26.92 | $72.68 |
| Plumber (Dupage (Argonne National Laboratories And Fermi National Laboratory), Grundy & Will Counties) | $60.50 | $39.02 | $99.52 |
| Plumber/Pipefitter (Dupage (Excluding Argonne National Laboratory And Fermi National Laboratory), Kane, And Kendall (Except The Mich-Wis Pumping Station In Milbrook, Silicas And Plant And Village Of Newark, Excludes Yorkville) Counties) | $41.20 | $29.15 | $70.35 |
| Pipefitter (Dupage (Argonne National Laboratories, And Fermi National Laboratory), Grundy, Lake, Mchenry & Will Counties) | $55.00 | $38.62 | $93.62 |
| Roofer (Dupage, Kane, Kendall, Lake, Mchenry, And Will Counties) | $50.25 | $30.43 | $80.68 |
| Roofer | $38.50 | $27.23 | $65.73 |
| Sprinkler Fitter (Dupage, Kane, Kendall, Lake, Mchenry, And Will Counties) | $63.25 | $36.50 | $99.75 |
| Sheet Metal Worker (Lake County) | $49.10 | $42.91 | $92.01 |
| Sheet Metal Worker: Aluminum Gutter Work (Lake County) | $31.32 | $37.02 | $68.34 |
| Sheet Metal Worker (Du Page, Grundy, Kane, Kendall, Mchenry, And Will Counties) | $56.35 | $38.65 | $95.00 |
| Truck Driver: 6 Axle Trucks (Grundy, Kendall, And Will Counties) Footnotes: A. $448.80 Health & Welfare Per Week, $562.80 Pension Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.67 | $0.30 | $46.97 |
| Truck Driver: 5 Axle Trucks (Grundy, Kendall, And Will Counties) Footnotes: A. $448.80 Health & Welfare Per Week, $562.80 Pension Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.47 | $0.30 | $46.77 |
| Truck Driver: 4 Axle Trucks (Grundy, Kendall, And Will Counties) Footnotes: A. $448.80 Health & Welfare Per Week, $562.80 Pension Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.27 | $0.30 | $46.57 |
| Truck Driver: 2 Or 3 Axle Trucks (Grundy, Kendall, And Will Counties) Footnotes: A. $448.80 Health & Welfare Per Week, $562.80 Pension Per Week. B. Lowboy Is An Additional $1.50 Per Hour An Additional $.20 Per Axle Shall Be Paid For All Vehicles With More Than Six (6) Axles | $46.12 | $0.30 | $46.42 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $45.09 | $13.40 | $58.49 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.89 | $13.40 | $58.29 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.69 | $13.40 | $58.09 |
| Holidays: New Year'S Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day. 900 Straight Time Hours Or More In 1 Calendar Year For The Same Employer Shall Receive 1 Week Paid Vacation; 3 Years - 2 Weeks Paid Vacation; 10 Years - 3 Weeks Paid Vacation; 20 Years - 4 Weeks Paid Vacation | $44.54 | $13.40 | $57.94 |
| Vacation | $45.86 | $0.30 | $46.16 |
| Vacation | $45.66 | $0.30 | $45.96 |
| Vacation | $45.46 | $0.30 | $45.76 |
| Vacation | $45.31 | $0.30 | $45.61 |
Always price from the wage determination attached to the solicitation (and any amendment): it is the one that applies to that contract. Rates shown are copied from the public SAM.gov documents; check the official document before you bid.