Davis-Bacon rates (construction)
Minimum pay for laborers and mechanics on federal and federally funded construction over $2,000 in Lafayette Excludes Flood Control County, Mississippi.
Davis-Bacon Heavy
Wage determination MS20260057, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Ironworker: Structural | $21.00 | $8.81 | $29.81 |
| Truck Driver: Dump Truck, Includes Water Sewer Lines | $12.00 | $0.00 | $12.00 |
| Operator: Bulldozer, Includes Water Sewer Lines | $17.60 | $0.00 | $17.60 |
| Operator: Backhoe/Excavator/Trackhoe, Includes Water Sewer Lines | $17.01 | $0.00 | $17.01 |
| Laborer: Pipelayer, Includes Water Sewer Lines | $13.19 | $0.00 | $13.19 |
| Laborer: Common Or General, Includes Water Sewer Lines | $12.17 | $0.00 | $12.17 |
| Ironworker, Reinforcing | $18.50 | $0.00 | $18.50 |
| Electrician | $19.36 | $7.70 | $27.06 |
| Cement Mason/Concrete Finisher, Includes Water Sewer Lines | $17.04 | $0.00 | $17.04 |
| Carpenter, Includes Form Work | $16.89 | $0.00 | $16.89 |
Always price from the wage determination attached to the solicitation (and any amendment): it is the one that applies to that contract. Rates shown are copied from the public SAM.gov documents; check the official document before you bid.