Davis-Bacon rates (construction)
Minimum pay for laborers and mechanics on federal and federally funded construction over $2,000 in Washington Excludes Heavy Dredging County, Oklahoma.
Davis-Bacon Heavy
Wage determination OK20260033, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Electrician | $51.00 | $23.80 | $74.80 |
| Power Equipment Operator: Group 9 Pumps | $28.25 | $19.05 | $47.30 |
| Power Equipment Operator: Group 8 Forklift;Tractor | $28.77 | $19.05 | $47.82 |
| Power Equipment Operator: Group 6 Rotary Drilling Machine When Operated From Console | $30.87 | $19.05 | $49.92 |
| Power Equipment Operator: Group 5 Bobcat/Skid Steer/Skid Loader | $32.71 | $19.05 | $51.76 |
| Power Equipment Operator: Group 4 Cranes With Boom Incl. Jib Less Than 100 Ft And Less Than 3 Cu. Yd.; Overhead Monorail Crane; Mechanic; Backhoe; Trackhoe; Grader/Blade; Power Driven Hole Digger With Less Than 30' Mast And Bulldozer | $34.07 | $19.05 | $53.12 |
| Power Equipment Operator: Group 3 All Crane Type Equipment 50 Ton Capacity And Larger Cranes, And Less Than 100 Ton Capacity. Crane Equipment (As Rated By Mfg.) 3 Cu. Yd. And Over Guy Derrick Whirley Power Driven Hole Digger (With 30' And Longer Mast) | $35.40 | $19.05 | $54.45 |
| Power Equipment Operator: Group 2 All Crane Type Equipment 100 Ton Capacity And Larger Cranes, And Less Than 200 Ton Capacity | $36.14 | $19.05 | $55.19 |
| Power Equipment Operator: Group 10 Oiler | $27.25 | $19.05 | $46.30 |
| Power Equipment Operator: Group 1 All Crane Type Equipment 200 Ton And Larger And Including 400 Ton Capacity Cranes. All Tower Cranes | $38.09 | $19.05 | $57.14 |
| Ironworker, Structural | $30.35 | $16.83 | $47.18 |
| Operator: Scraper | $14.00 | $0.00 | $14.00 |
| Laborer: Pipelayer | $13.29 | $0.00 | $13.29 |
| Laborer: Common Or General | $12.41 | $0.00 | $12.41 |
| Carpenter (Form Work Only) | $14.00 | $0.00 | $14.00 |
| Truck Driver ((3) Flatbed Truck) | $30.85 | $16.65 | $47.50 |