Davis-Bacon rates (construction)
Minimum pay for laborers and mechanics on federal and federally funded construction over $2,000 in Barnwell Counties County, South Carolina.
Davis-Bacon Heavy
Wage determination SC20260001, revision 1, updated 0. Basic hourly rate plus fringe benefit per hour.
| Trade | Rate | Fringe | Total / hour |
|---|---|---|---|
| Truck Driver | $7.25 | $0.00 | $7.25 |
| Power Equipment Operators: Motor Grader | $7.25 | $0.00 | $7.25 |
| Power Equipment Operators: Mechanic | $7.25 | $0.00 | $7.25 |
| Power Equipment Operators: Front End Loader | $7.25 | $0.00 | $7.25 |
| Power Equipment Operators: Dragline | $7.25 | $0.00 | $7.25 |
| Power Equipment Operators: Crane | $7.98 | $0.00 | $7.98 |
| Power Equipment Operators: Bulldozer | $7.25 | $0.00 | $7.25 |
| Power Equipment Operators: (Pan Scraper) | $7.25 | $0.00 | $7.25 |
| Power Equipment Operators: (Backhoe) | $7.25 | $0.00 | $7.25 |
| Pipefitter | $9.09 | $0.00 | $9.09 |
| Manhole Builder | $7.25 | $0.00 | $7.25 |
| Line Construction: Line Technician | $10.08 | $0.00 | $10.08 |
| Laborers: General | $7.25 | $0.00 | $7.25 |
| Laborers: (Pipelayer) | $7.25 | $0.00 | $7.25 |
| Laborers: (Chain Saw) | $7.25 | $0.00 | $7.25 |
| Ironworker | $10.98 | $0.00 | $10.98 |
| Cement Mason/Concrete Finisher | $7.25 | $0.00 | $7.25 |
| Carpenter | $7.42 | $0.00 | $7.42 |
| Bricklayer | $7.25 | $0.00 | $7.25 |
| Boilermaker (Tank Work) | $12.96 | $3.32 | $16.28 |
Always price from the wage determination attached to the solicitation (and any amendment): it is the one that applies to that contract. Rates shown are copied from the public SAM.gov documents; check the official document before you bid.